Lepidico has recommenced exploration within the 293km2 over which it has prospecting rights at Karibib, with a view to increasing its resource to a size that is sufficient to a) extend the Phase 1 Plant project operating life to more than 20 years and b) support a Phase 2 Plant. Management’s initial target is to increase the combined resource at Helikon 2-5 from 2.2Mt to 5.0–7.0Mt, which it believes would be sufficient to support a Phase 2 Plant of approximately the same size as its Phase 1 plant of c 5,000tpa, which could be located in either Namibia, Europe or North America (note that this compares with the aggregate tonnage of 9.0Mt at Rubicon 1 and Helikon 1 currently dedicated to supporting the Phase 1 plant). Beyond this, management believes that a 10–12Mt resource inventory would support a c 10,000tpa Phase 2 plant. However, the ostensible goal of the programme is to delineate a resource of c 25Mt, which management estimates could support a full 20,000tpa Phase 2 plant. However, where before this was conceived as a fully integrated, purely owner-operated project, in recent months Lepidico reports that it has received unsolicited enquiries from as many as four junior explorers in or near the Atlantic basin that have been exploring pegmatite fields and identifying lepidolite-rich mineralisation. Several of these are reported to be in the process of being drilled and a number have sent samples to Lepidico to ascertain their material’s amenability to its proprietary L-Max and LOH-Max processes. To expedite development, therefore, rather than seeking to license its technology, Lepidico is in the process of investigating the construction of a P2P specifically designed to handle concentrate from third-party sources in conjunction with material from an expansion at Karibib.
According to its Phase 1 Plant project DFS (see Valuation update post-feasibility study, published on 20 July 2020), Lepidico will mine c 0.5Mt ore pa at an average life-of-mine strip ratio of 3.8 to produce c 60kt of concentrate pa at an average grade of 3.23% lithium oxide after a (lithium) recovery to concentrate of 80.6%. The chemical plant will then process c 56,700t concentrate (dry) pa to produce up to 5,600tpa lithium hydroxide monohydrate. As mining encounters lower-grade material in the lower horizons of Rubicon, however, the plant has been designed to accommodate a near doubling in throughput rates by the eighth year of the project via the addition of an additional leach tank. Over the life of its operation, ore mined for the Phase 1 Plant project is estimated to amount to 6.6Mt, or 73.0% of combined Rubicon 1 and Helikon 1 in-situ tonnage. By contrast, a Phase 2 plant with the capacity to produce 20,000tpa of lithium carbonate equivalent, or 22,717tpa lithium hydroxide monohydrate equivalent, would require an in-situ tonnage of 19.2Mt ore pro rata, which would be presumed to originate from Lepidico’s other deposits at Karibib (ie Helikon 2-5), new discoveries in the Karibib mining and prospecting licence areas (see below) and third-party mines.
The existing resource at Helikon 2-5 amounts to 2.2Mt at an average grade of 0.41% lithium oxide:
Exhibit 1: Mineral resource estimate, Helikon 2-5 (January 2020)
Deposit |
Category |
Cut-off grade (% Li2O) |
kt |
Grade (% Li2O) |
Contained Li2O |
Contained LCE |
Helikon 2 |
Inferred |
0.20 |
216.0 |
0.56 |
1,210 |
2,991 |
Helikon 3 |
Inferred |
0.20 |
295.0 |
0.48 |
1,416 |
3,501 |
Helikon 4 |
Inferred |
0.20 |
1,510.0 |
0.38 |
5,738 |
14,189 |
Helikon 5 |
Inferred |
0.20 |
179.0 |
0.31 |
555 |
1,372 |
Total |
Inferred |
0.20 |
2,200.0 |
0.41 |
8,919 |
22,054 |
Source: Lepidico, Edison Investment Research. Note: LCE = lithium carbonate equivalent.
At 0.41% lithium oxide, the average grade of Helikon 2-5 compares well with the average resource grade of Rubicon 1 and Helikon 1 combined of 0.43% and the average reserve grade of Rubicon 1 and Helikon 1 combined of 0.46%. Current exploration work at Karibib is focusing on Helikon 4 and pushing down strike towards Helikon 3 and Helikon 2, with a target of delineating an additional 4–5Mt of ore at a grade of 0.5% lithium oxide (Li2O). Within this context, on 27 June, Lepidico announced that drilling at Helikon 4 had returned the broadest high-grade lithium intercepts to date at Karibib, while a new lepidolite-bearing pegmatite had also been identified at the Homestead prospect with a strike of at least 250m and a downhole width of up to 31m. Precise details of its drilling results are included in its announcement. However, highlights of the programme to date have been:
■
Broad intercepts of lepidolite mineralisation at Helikon 4, including 40m at a grade of 1.08% Li2O and 20m at 1.16% Li2O.
■
A weighted average intercept grade of 0.60% Li2O from new drilling (cf an existing inferred resource grade of 0.38% Li2O – see Exhibit 1, above), which has also extended the zone of mineralisation at Helikon at depth, where it remains open.
■
A new lepidolite-bearing pegmatite confirmed by reverse circulation drilling at the Homestead prospect, 1.6km along strike from Helikon 2-5 (which is currently being chased down plunge).
■
The completion of trenching and sampling of Rubicon stockpiles with the intention of contributing to an updated mineral resource estimate with additional tonnage in the indicated category in particular to allow it to be included in the Phase 1 mine plan.
■
Regional exploration has been successful in identifying blind pegmatite targets under surface cover and scout drilling is now seeking lithium mica mineralisation associated with associated surface rubidium anomalies.
Preparation is also underway to start exploration activities to the east of EPL5439 on several priority lithium and gold targets. Exploration there is intended to continue throughout 2023, with the aim of expanding resources to support a significantly larger Phase 2 Plant project. However, turnaround times for assay results have been slow – which is a global issue – and it has become increasingly apparent to management that the best means of expediting the Phase 2 Plant project may be to employ otherwise redundant material at third-party sites, while continuing to expand resources at Karibib, albeit in a more structured manner.
Revised Phase 2 project economics
We have provided a conceptual, risk-adjusted valuation for Lepidico’s Phase 2 Plant project on two previous occasions – the first in June 2021 when we valued the project at US$594.7m, unrisked but fully diluted (see Phase 2 coming into view, published on 18 June 2021) and the second, in February 2022, when we valued it at US$851.9m or 0.73-1.77 Australian cents per share after we had updated our long-term lithium price forecasts (see Big swings and small roundabouts, published on 16 February 2022). In formulating these valuations, we made the following assumptions:
■
The geological characteristics of the Phase 2 Plant project orebody approximated those of Karibib, but scaled up to support a mining rate 2.9x the Phase 1 project operation. The stripping ratio, ore grade, recovery and mass pull were all assumed to be the same as the Phase 1 operation to result in 2.9x the production of concentrate.
■
Production and consumption of concentrate into end-products was assumed to be in balance (ie negligible stockpiles of concentrate were presumed to be created).
■
Output from the chemical plant was assumed to be 20,000tpa lithium carbonate equivalent (LCE), or 22,717tpa lithium hydroxide monohydrate equivalent, with the production of end-products (lithium hydroxide monohydrate, rubidium sulphate, caesium formate, sulphate of potash and amorphous silica) assumed to be pro rata to the Phase 1 Abu Dhabi chemical plant production profile.
■
Unit mining and processing costs were assumed to be the same as for the Karibib and Abu Dhabi chemical plant operations, with the exception that 70% of costs were presumed to be variable (and scaled up 2.9x therefore) and 30% were assumed to be fixed and therefore invariant to scale.
■
In March 2021, Lepidico quoted scoping study design parameters as indicating a capital intensity of US$16,900/t LCE or US$10,500/t after credits for a 20,000tpa LCE plant operation (note: for these purposes, capital intensity was defined as pre-production capital per tonne of annual LCE plus by-products adjusted to lithium hydroxide equivalent). On this basis, we estimated initial capex for the Phase 2 plant of US$238.5m (being 10,500 x 22,717) plus capex for the mine (all distributed over three years). In this case, we assumed that capex for the mine would be pro rata to the Karibib mining and concentrating operation and would amount to US$124.2m. We therefore estimated total pre-production capex of US$362.8m, or US$15,972/t lithium hydroxide monohydrate equivalent to be funded from retained earnings from the Phase 1 Plant project (ie with no additional assumed dilution), which compared with an equivalent figure of US$139.0m and US$17,758/t for the Phase 1 Plant project (Edison calculation excluding working capital). Sustaining capital was assumed to be pro rata to the Phase 1 Plant project.
■
Depreciation was assumed to be over 10 years.
■
The corporate tax rate was assumed to be the global average corporate tax rate of 23.65% (source: KPMG corporate tax rate tables for 2021–22).
The resulting valuations were then risk adjusted for a) their stage of development (which was deemed to be ‘scoping study’ stage) and/or b) their resources relative to those required to support a 20,000tpa LCE Phase 2 plant.
For the purposes of our revised and updated Phase 2 Plant project valuation, we have left these assumptions unchanged with the following modifications:
■
Of the increase in scale required by the Phase 2 Plant relative to the Phase 1 Plant, we have assumed that 1.0x of the 2.9x factor involved will be supported by resources at Karibib – and more specifically at Helikon 2-5 – and that the additional 1.9x factor will be supported by resources from third parties. Note that this updated assumption affects our tax and capex assumptions, as well as our (integrated) operating cost assumptions.
■
As a consequence of the above, rather than assuming that concentrate will be delivered to the plant from a fully integrated owner-operated mine, we are now assuming that it will be purchased from a third-party supplier (on the same basis that Lepidico’s chemical plant will purchase lithium mica concentrate from the Karibib mine), which inevitably acts to increase variable costs.
All other things being equal, our estimate of indicative Phase 2 Plant project economics in a typical year (relative to previous estimates), is as shown in Exhibit 2, below.
Exhibit 2: Conceptual Phase 2 Plant project income statement
US$m pa |
Ore from third-party sources (August 2022) |
Revised lithium price (February 2022) |
Original estimate (June 2021) |
Revenue |
365.6 |
365.6 |
356.4 |
Fixed costs |
15.1 |
15.1 |
19.2 |
Variable costs |
128.0 |
102.5 |
130.2 |
Gross profit |
222.5 |
248.1 |
207.0 |
Depreciation |
29.4 |
38.2 |
36.3 |
EBIT |
193.1 |
209.9 |
170.7 |
Interest |
- |
- |
- |
Pre-tax profit |
193.1 |
209.9 |
170.7 |
Tax |
47.5 |
49.6 |
40.4 |
Tax (%) |
23.65 |
23.65 |
23.65 |
Profit after tax |
145.6 |
160.3 |
130.3 |
|
|
|
|
Free cash-flow |
175.1 |
198.4 |
166.6 |
|
|
|
|
Sustaining capex |
3.5 |
4.8 |
4.8 |
|
|
|
|
Net cash-flow |
171.6 |
193.6 |
161.8 |
Source: Edison Investment Research, Lepidico
Discounting 20 years’ worth of cash flows of this order of magnitude back to present value at a discount rate of 10% and subtracting US$281.4m in initial capex (cf US$362.8m previously) yields a preliminary theoretical value for the Phase 2 Plant project of US$783.6m (cf US$851.9m previously) at the start of capex, or US$0.0919/share (cf US$0.1088/share previously), post-assumed FY23 equity funding. Readers should note that significant exploration success at Karibib or the acquisition of another in-ground asset could result in a vertically integrated Phase 3 Project, which is consistent with Lepidico’s growth ambitions. At this stage, we are choosing not to model such a concept. However, as before, there remains considerable value upside from royalties associated with process technology licensing.
Risked conceptual Phase 2 Plant project
As before, we have applied two methods to adjust the above valuation to reflect risk to the Phase 2 Plant project implementation.
Method 1: Stage of development risk
The capital intensity estimate for the Phase 2 Plant is quoted as being performed to ‘scoping study design parameters’, while the operational cost estimates are compiled to a DFS standard – albeit there is no guarantee that either the mining or the chemical cost portions of a Phase 2 Plant project would approximate those at Karibib and Abu Dhabi, respectively. As such, a preliminary economic assessment (PEA) level risk factor applied to our valuation (above) could be appropriate in formulating a risk-adjusted valuation for a conceptual Phase 2 Plant project. Alternatively, it could be stated that we believe our valuation to be correct in the event that the assumed parameters are confirmed in a PEA or scoping-level study. In our report Gold stars and black holes, we calculated a mean enterprise value for companies with projects at the PEA or scoping study stage of development of 11.7% of project net present value (NPV). This would imply an immediate valuation for the Phase 2 Plant project of US$91.7m, or 1.08 US cents per share (1.55 Australian cents per share) post-assumed FY23 equity funding.
In order to support a 20,000tpa LCE chemical plant operation, we estimate that a 1.7Mtpa ore processing capacity would be required. Over 20 years, this would imply a required ore reserve of c 34Mt (at a similar grade to the current ore reserve) which, at the existing reserve:resource conversion ratio at Rubicon 1 and Helikon 1 of 74.3% (by tonnage), would imply a minimum resource of 45.9Mt at an acceptable minimum grade to support a Phase 2 plant. This compares with a current resource at Helikon 2-5 of 2.2Mt (see Exhibit 1) or 4.8% of that ultimately required. Invoking this percentage as an appropriate measure to apply to the valuation of US$783.6m implies a risked valuation of US$37.5m, which equates to 0.44 US cents per share or 0.63 Australian cents per share (post-assumed FY23 equity funding). In this case, however, resources contributed by third parties to the Phase 2 Plant project may increase much more rapidly than at Karibib alone under the fully integrated, owner-operator model.
Third-party model timing and implementation considerations
Management estimates that the use of third-party ore to feed into the Phase 2 Plant could take two to three years out of a typical mine-concentrator project development timeline.
In the first instance, Lepidico will require approximately one year in which to upgrade its resource at Helikon from the inferred category into the measured and indicated categories, and thence into the proven and probable categories of reserves. As presently conceived, the Karibib Phase 1 Plant project has the following attributes:
■
It already has road access to the project.
■
It has water rights over twice its planned requirements.
■
The installed power line has capacity for twice the project’s electricity requirements.
■
Its cyclones have twice the capacity required for the anticipated throughput.
■
It has already been designed to accommodate a doubling in throughput rates by the eighth year of the project.
Doubling the capacity of the Karibib concentrator earlier than originally planned will therefore require little more than the already planned expansion (see page 2) to be brought forward plus an additional ball mill, with the result that it should be relatively easy and very capital efficient.
Thereafter, Lepidico will embark on approximately two years of engineering works, which should be abundant time for a third party to delineate an appropriate resource to contribute to the Phase 2 Plant. Once delineated, the third party would then conduct a feasibility study on its mining and concentration project incorporating Lepidico’s concentrator design.
By mid-2024, therefore, Lepidico should have an appreciation of the potential resources available to contribute to the Phase 2 Plant project, at the same time as its chemical plant in Abu Dhabi is coming on-steam. As such, it would be in a position to undertake the front-end engineering and design (FEED) aspects of its own feasibility on the larger Phase 2 Plant project within the context of its actual experience of the operation of the Abu Dhabi plant. On this basis, it is possible that the development of the Phase 2 Plant project could occur as early as CY27.