The effect of the MKFL and Ikenskoe-Sobolevsky resource upgrades on the Kun-Manie project as a whole is to increase the mineralised tonnage by 32.1% and contained nickel by 11.6% (see Exhibit 7, overleaf) and the measured and indicated component of the resource by 99.8%, albeit mostly as a result of the more significant MKFL upgrade (in both absolute and percentage terms).
Exhibit 7: Kun-Manie resource upgrade (May 2016 vs April 2015)
|
Tonnage (Mt) |
Grade Ni (%) |
Contained Ni (t) |
Grade Cu (%) |
Contained Cu (t) |
Grade Pt (g/t) |
Contained Pt (t) |
Grade Pd (g/t) |
Contained Pd (t) |
Kun-Manie (May 2016) |
|
|
|
|
|
|
|
|
|
Measured |
18.3 |
0.51 |
93,300 |
0.14 |
25,600 |
0.2 |
3.4 |
0.2 |
3.6 |
Indicated |
88.5 |
0.44 |
385,800 |
0.12 |
109,900 |
0.1 |
9.3 |
0.1 |
9.8 |
Measured & indicated |
106.9 |
0.45 |
479,200 |
0.13 |
135,500 |
0.1 |
12.8 |
0.1 |
13.6 |
Inferred |
52.8 |
0.47 |
246,900 |
0.13 |
70,800 |
0.1 |
7.2 |
0.1 |
7.1 |
Total |
159.6 |
0.45 |
726,000 |
0.13 |
206,400 |
0.1 |
19.8 |
0.1 |
20.5 |
|
|
|
|
|
|
|
|
|
|
Kun-Manie (April 2015) |
|
|
|
|
|
|
|
|
|
Measured |
15.7 |
0.52 |
81,800 |
0.13 |
21,100 |
0.2 |
2.9 |
0.2 |
3.2 |
Indicated |
37.8 |
0.56 |
210,500 |
0.15 |
57,000 |
0.1 |
4.6 |
0.1 |
5.3 |
Measured & indicated |
53.5 |
0.55 |
292,300 |
0.15 |
78,100 |
0.1 |
7.5 |
0.2 |
8.5 |
Inferred |
67.3 |
0.53 |
358,300 |
0.15 |
100,300 |
0.1 |
9.4 |
0.1 |
9.5 |
Total |
120.8 |
0.54 |
650,600 |
0.15 |
178,400 |
0.1 |
16.9 |
0.1 |
18.0 |
|
|
|
|
|
|
|
|
|
|
Change (units) |
|
|
|
|
|
|
|
|
|
Measured |
2.6 |
-0.01 |
11,500 |
0.01 |
4,500 |
0.0 |
0.5 |
0.0 |
0.4 |
Indicated |
50.7 |
-0.12 |
175,300 |
-0.03 |
52,900 |
0.0 |
4.7 |
0.0 |
4.5 |
Measured & indicated |
53.4 |
-0.10 |
186,900 |
-0.02 |
57,400 |
0.0 |
5.3 |
0.0 |
5.1 |
Inferred |
-14.5 |
-0.06 |
-111,400 |
-0.01 |
-29,500 |
0.0 |
-2.3 |
0.0 |
-2.4 |
Total |
38.8 |
-0.08 |
75,400 |
-0.02 |
28,000 |
0.0 |
2.9 |
0.0 |
2.5 |
|
|
|
|
|
|
|
|
|
|
Change (percent) |
|
|
|
|
|
|
|
|
|
Measured |
16.6 |
-2.1 |
14.1 |
4.1 |
21.3 |
-0.3 |
16.2 |
-3.2 |
12.8 |
Indicated |
134.1 |
-21.7 |
83.3 |
-17.6 |
92.8 |
-12.9 |
103.9 |
-20.7 |
85.7 |
Measured & indicated |
99.8 |
-18.0 |
63.9 |
-13.2 |
73.5 |
-14.4 |
71.1 |
-20.2 |
59.4 |
Inferred |
-21.5 |
-12.2 |
-31.1 |
-10.0 |
-29.4 |
-3.4 |
-24.2 |
-5.4 |
-25.8 |
Total |
32.1 |
-15.5 |
11.6 |
-12.4 |
15.7 |
-11.2 |
17.3 |
-13.8 |
13.9 |
Source: Amur Minerals, Edison Investment Research
For the amount of drilling done, the increase in the resource equates to 6,665t of mineralised material and 13.0t of contained nickel per metre drilled, on average.
At the prevailing prices of the contained metals in question (namely US$9,295/t Ni, US$1,256/oz Au, US$4,942/t Cu, US$1,064/oz Pt and US$628/oz Pd), the total Kun-Manie resource equates to 953.2kt of contained nickel equivalent (NiE) or 7.1Moz of gold equivalent (AuE). Note that the figure of 7.1m gold equivalent ounces would have been 7.8Moz AuE if we used the same metals’ prices as in our December 2015 note (in which we calculated a gold equivalent resource of 6.9Moz at the time).
In the aftermath of the resource upgrade, MKFL now accounts for 51% of the total resource at Kun-Manie, compared with 45% beforehand, while Ikenskoe-Sobolevsky has declined from 27% to 25% of the total, on account of the proportionately larger MKFL increase.
Exhibit 8: Kun-Manie resource by deposit (% based on contained nickel)
|
|
Source: Amur Minerals, Edison Investment Research
|
At the time of our December update note, Amur’s enterprise value equated to US$58.67 per tonne of contained nickel (including by-products), on which basis the increase in the resource of 72,400t of contained nickel should be worth US$4.4m to the company (compared with a US$3.3m cost of the exploration associated with defining the additional resource).
In the context of the broader mineralisation at Kun-Manie, the 2015 exploration drilling at Flangovy in particular could be interpreted as being indicative of a single, continuous corridor of mineralisation, approximately 2.5km long, 20-30m thick and at an in-situ grade from 0.7-0.9% nickel, running from Maly Kurumkon through Flangovy to Gorny. It is also possible that there is another similar such corridor from Ikenskoe-Sobolevsky to Kubuk. Amur’s upcoming 2016 field season will again be focused on the MKFL deposit, at which two categories of work will be pursued, including resource-related drilling and metallurgical sample collection.
Thereafter, now that the inferred resource at MKFL has been upgraded to indicated status, the largest remaining resource in the inferred category is at Kubuk, where up to 17.1Mt of material is targeted for upgrade to indicated status. Future drill programmes will be directed towards applying a similar differentiated high-grade/low-grade domain interpretation to the mineralisation at Kubuk and will focus on similarly upgrading these resources via an estimated 7-8km in-fill drill programme. To this end, drill sites have been identified and variously prepared at Sobolevsky with a view to determining the continuity of a 20m thick, >1% nickel outcrop in the direction Kubuk (see below). Note that Vodorazdelny is not a candidate to be remodelled since it is intended to be mined by open cast methods alone and Gorny is similarly not a candidate owing to the fact that its grade is too low.
In addition to the in-fill programme at Kubuk, there is potential for a step-out programme to the east and down-dip below 400m. Together with its existing LF-70, Amur’s recent purchase of a Boart Longyear LF-90 drill rig will double the number of metres that it can drill in a season to c 15,000m. This represents a 40% increase in the total metres drilled since the acquisition of Amur’s original exploration licence in 2004. Pro-rata to its most recent upgrade, a drill programme of 15,000m in the 2016 field programme could be expected to yield a 100.0Mt increase in mineralised tonnage, containing 194,283t of contained nickel. Simultaneously, two new D9R Caterpillar bulldozers (effectively representing a seed capital fleet) have been mobilised to set up ready access along the full length of the Kurumkon trend in preparation for pre-production development.
Exhibit 9: The five currently defined exploration areas at Kun-Manie
|
|
|
SRK is using Leapfrog technology to build a high-grade model at Kubuk, which will allow the definition of simulated mining units (SMUs) to an accuracy of 5mx5m and ultimately allow Amur to generate a mining schedule and model for the deposit.
In the meantime, metallurgical recovery results from samples of ore from MKFL are reported to be nearing completion and will be used to define reserves in due course, while samples from Kubuk have been assayed for metallurgical recoveries (note, having previously been assayed for grindability and crushing energy requirements). Since the samples are deemed to be high-grade (>1%) nickel, they are required by the Russian authorities to be assayed twice.
Once the required exploration has been completed, Amur will announce an upgraded JORC-compliant resource to the market. It will then set about optimising its projected production schedule (including a JORC reserve), which is now likely to involve advancing the mining of high grade, underground ore in its mine plan and could thereby materially affect the economics of the project and the most efficient approach to its exploitation.
The Far East and Baikal Region Development Fund
In March, Amur announced the signing of a non-binding Heads of Terms Agreement with the Russian government’s Far East and Baikal Region Development Fund. In broad terms, the agreement expresses the intention of the fund and the company to expand their collaboration on funding Kun-Manie and provides a starting point for detailed negotiations establishing technical feasibility requirements, funding needs, terms and conditions and timelines.
In particular, in conjunction with the existing mandate for fundraising from potential strategic partners in Russia, China, and India (which continues to be the cornerstone of Amur’s strategy), the agreement expands the funding scope to include the prospect of federal financing of overall mine, plant and smelter development, as well as potential state funding of infrastructure.
The fund typically participates in infrastructure, such as the required 320km road from the Baikal Amur railhead at Verkhnezeisk to the Kun-Manie site and the extension of an existing power line to the location of the planned smelting facilities (located close to the rail spur from the BAM line to the Elga coal project in Yakutia). If implemented, the concurrent development of road and smelter facilities could result in the development of a new industrial hub in Amur Oblast, in which Amur Minerals would play in central role.
Once the full feasibility study is completed and the project is financed, Amur envisages a two-year construction period in CY18 and CY19 before first production of nickel in CY20. According to a Russian TEO, development could, in turn, lend the project naturally to Russian project finance, in which case management has suggested that an 80:20 debt:equity financing structure could be achievable. However, it is understood that Amur is also investigating the potential to access funding via a streaming arrangement relating to its by-products, in particular. Note that streaming is associated with less risk than debt (and is not considered as debt by lending banks), as it has neither a fixed repayment schedule nor associated debt-service covenants.
In the meantime, management continues to work on improving the operational blueprint published in June 2015 (and which built on the earlier, conceptual open-pit study). Currently, it envisages that Ikenskoe-Sobolevsky would support an open-pit mining operation, that Kubuk would support an open-pit and underground mining operation and that Maly-Kurumkon would support an open-pit mining operation, but that this would transition into underground mining at Flangovy. In addition, it believes that it has identified a potential c US$150m in capex savings, which could then be used to invest in a flash smelter (vs the electric furnace smelter and converter smelter configuration currently envisaged).