The effect of the Kubuk resource upgrades (as well as those for MKFL and IKEN) on the Kun-Manie project as a whole is to increase the mineralised tonnage by 36.3% and contained nickel by 13.8% and the measured and indicated component of the resource by exactly 100.0% (albeit principally as a result of the MKFL upgrade).
Exhibit 4: Kun-Manie resource upgrade (May 2016 vs April 2015)
|
Tonnage (Mt) |
Grade Ni (%) |
Contained Ni (t) |
Grade Cu (%) |
Contained Cu (t) |
Grade Pt (g/t) |
Contained Pt (t) |
Grade Pd (g/t) |
Contained Pd (t) |
Kun-Manie (May 2016) |
|
|
|
|
|
|
|
|
|
Measured |
18.3 |
0.51 |
93,300 |
0.14 |
25,600 |
0.2 |
3.4 |
0.2 |
3.7 |
Indicated |
88.7 |
0.44 |
390,900 |
0.12 |
111,100 |
0.1 |
9.6 |
0.1 |
10.2 |
Measured & indicated |
107.0 |
0.45 |
484,100 |
0.13 |
136,600 |
0.1 |
13.0 |
0.1 |
13.9 |
Inferred |
57.7 |
0.44 |
255,900 |
0.13 |
76,200 |
0.1 |
7.7 |
0.1 |
7.8 |
Total |
164.7 |
0.45 |
740,100 |
0.13 |
212,900 |
0.1 |
20.6 |
0.1 |
21.7 |
|
|
|
|
|
|
|
|
|
|
Kun-Manie (April 2015) |
|
|
|
|
|
|
|
|
|
Measured |
15.7 |
0.52 |
81,800 |
0.13 |
21,100 |
0.2 |
2.9 |
0.2 |
3.2 |
Indicated |
37.8 |
0.56 |
210,500 |
0.15 |
57,000 |
0.1 |
4.6 |
0.1 |
5.3 |
Measured & indicated |
53.5 |
0.55 |
292,300 |
0.15 |
78,100 |
0.1 |
7.5 |
0.2 |
8.5 |
Inferred |
67.3 |
0.53 |
358,300 |
0.15 |
100,300 |
0.1 |
9.4 |
0.1 |
9.5 |
Total |
120.8 |
0.54 |
650,600 |
0.15 |
178,400 |
0.1 |
16.9 |
0.1 |
18.0 |
|
|
|
|
|
|
|
|
|
|
Change (units) |
|
|
|
|
|
|
|
|
|
Measured |
2.6 |
-0.01 |
11,500 |
0.01 |
4,500 |
0.0 |
0.5 |
0.0 |
0.5 |
Indicated |
50.9 |
-0.12 |
180,400 |
-0.04 |
54,100 |
0.0 |
5.0 |
0.0 |
4.9 |
Measured & indicated |
53.5 |
-0.09 |
191,800 |
-0.02 |
58,500 |
0.0 |
5.6 |
0.0 |
5.4 |
Inferred |
-9.6 |
-0.09 |
-102,400 |
-0.02 |
-24,100 |
0.0 |
-1.7 |
0.0 |
-1.7 |
Total |
43.9 |
-0.09 |
89,500 |
-0.02 |
34,500 |
0.0 |
3.7 |
0.0 |
3.7 |
|
|
|
|
|
|
|
|
|
|
Change (percent) |
|
|
|
|
|
|
|
|
|
Measured |
16.6 |
-2.1 |
14.1 |
4.1 |
21.3 |
-0.3 |
16.2 |
-0.6 |
15.9 |
Indicated |
134.7 |
-20.9 |
85.7 |
-23.6 |
94.9 |
-10.5 |
110.0 |
-17.7 |
93.0 |
Measured & indicated |
100.0 |
-17.2 |
65.6 |
-12.5 |
74.9 |
-12.6 |
74.9 |
-18.0 |
64.0 |
Inferred |
-14.3 |
-16.7 |
-28.6 |
-11.4 |
-24.0 |
-4.9 |
-18.5 |
-4.3 |
-18.0 |
Total |
36.3 |
-16.6 |
13.8 |
-12.5 |
19.3 |
-10.4 |
22.2 |
-11.5 |
20.7 |
Source: Amur Minerals, Edison Investment Research
For the amount of drilling performed, the increase in the resource equates to 7,541t of mineralised material and 15.4t of contained nickel per metre drilled on average over the three deposits (NB Management estimates its all-in cost of drilling to be US$75-100 per metre drilled, including that performed for bulk metallurgical testwork).
At the prevailing prices of the contained metals in question (namely US$8,330/t Ni, US$4,562/t Cu, US$1,006/oz Pt and US$547/oz Pd), the total Kun-Manie resource equates to 982.7kt of contained nickel equivalent (NiE).
In the aftermath of the Kubuk resource upgrade, MKFL now accounts for 50% of the total Kun-Manie resource (vs 45% beforehand), while Ikenskoe-Sobolevsky has declined from 27% to 24% and Kubuk remains unchanged, at 18%.
Exhibit 5: Kun-Manie resource by deposit (% based on contained nickel)
|
|
Source: Amur Minerals, Edison Investment Research
|
At the time of our December update note, Amur’s enterprise value equated to US$58.67 per tonne of contained nickel (including by-products), on which basis the increase in the Kun-Manie resource of 89,500t of contained nickel as a result of Amur’s efforts should be worth US$5.3m to the company (compared to the US$3.3m cost of the associated exploration).
From the perspective of Russia’s legal framework, Amur is operating under the auspices of a temporary TEO (note, a Russian TEO equates to a western feasibility study) – the ‘temporary’ nature of the TEO allowing Amur to conclude its exploration activities. The key piece of work to upgrade the status of its TEO from ‘temporary’ to ‘permanent’ is a bulk sample, which Amur is prioritising for 2016. In this case, it is likely to be in the form of a core bulk sample that is large enough for a pilot plant test to determine the metallurgical characteristics of the concentrate produced. Management has stated that it is prepared to fly the bulk sample out from site by helicopter if necessary (a 20t bulk sample would require approximately eight helicopter flights to transport). As a result, Amur believes it will be possible to produce a definitive feasibility study to both Russian (more onerous re permitting etc) and western standards (more onerous re social, environmental and economic standards etc) in 15-21 months (ie in H217).
For the purposes of finalising its DFS, SRK is completing a full geological and field procedure review of Amur’s operations at Kun-Manie.
In the context of the broader mineralisation at Kun-Manie, the 2015 exploration drilling at Flangovy in particular could be interpreted as being indicative of a single, continuous corridor of mineralisation, approximately 2.5km long, 20-30m thick and at an in-situ grade from 0.7-0.9% nickel, running from Maly Kurumkon through Flangovy to Gorny. It is also possible that there is another similar such corridor from Ikenskoe-Sobolevsky to Kubuk. As a result, it is Amur’s intention to continue drilling at Kun-Manie into the foreseeable future. Amur’s upcoming 2016 field season is expected to start early (on account of prevailing clement weather conditions) and will again be focused on the MKFL deposit, at which two categories of work will be pursued, including resource related drilling (both in-fill and step-out) and metallurgical and rock mechanics sample collection in support of mine design parameters.
Thereafter, the focus of future drill programmes will be towards similarly upgrading and expanding resources at Kubuk via an estimated 7-8km in-fill drill programme. To this end, drill sites have been identified and variously prepared at Sobolevsky with a view to determining the continuity of a 20m thick, >1% nickel outcrop in the direction Kubuk (see below). Vodorazdelny is not a candidate to be remodelled since it is intended to be mined by open-cast methods alone and Gorny is similarly not a candidate owing to the fact that its grade is too low.
In addition to a future in-fill programme at Kubuk, there is also potential for a step-out programme to the east and down-dip below 400m. Together with its existing LF-70, Amur’s recent purchase of a Boart Longyear LF-90 drill rig will double the number of metres that it can drill in a season to c 15,000m. This represents a 40% increase in the total metres drilled since the acquisition of Amur’s original exploration licence in 2004. Pro-rata to the May 2016 Kun-Manie resource upgrade, a drill programme of 15,000m could be expected to yield a 113.1Mt increase in mineralised tonnage, containing 230,615t of contained nickel. Simultaneously, two new D9R Caterpillar bulldozers (effectively representing a seed capital fleet) have been mobilised to set up ready access along the full length of the Kurumkon trend in preparation for pre-production development.
Exhibit 6: The five currently defined exploration areas at Kun-Manie
|
|
|
SRK used Leapfrog technology to build the high-grade model at Kubuk, which will allow the definition of simulated mining units (SMUs) to an accuracy of 5mx5m and ultimately allow Amur to generate a mining schedule and model for the deposit.
To date, testing has determined that each deposit has different metallurgical recoveries. As a result, SGS is updating grade-recovery curves for each of the deposits to determine the recoverable metal to be extracted to concentrate by the ore treatment facility. As soon as this is complete, Amur will award reserve definition stage work to an independent consultant to be performed to DFS standards, followed by an integrated mine plan and optimised schedule. This is likely to involve advancing the mining of high grade, underground ore and could therefore materially affect the economics of the project compared to that currently envisaged.
The Far East and Baikal Region Development Fund
In March, Amur announced the signing of a non-binding Heads of Terms Agreement with the Russian government’s Far East and Baikal Region Development Fund. In broad terms, the agreement expresses the intention of the fund and the company to expand their collaboration on funding Kun-Manie and provides a starting point for detailed negotiations establishing technical feasibility requirements, funding needs, terms and conditions and timelines.
In particular, in conjunction with the existing mandate for fundraising from potential strategic partners in Russia, China, and India (which continues to be the cornerstone of Amur’s strategy), the agreement expands the funding scope to include the prospect of federal financing of overall mine, plant and smelter development, as well as potential state funding of infrastructure.
The fund typically participates in infrastructure, such as the required 320km road from the Baikal Amur railhead at Verkhnezeisk to the Kun-Manie site and the extension of an existing power line to the location of the planned smelting facilities (located close to the rail spur from the BAM line to the Elga coal project in Yakutia). If implemented, the concurrent development of road and smelter facilities could result in the development of a new industrial hub in Amur Oblast, in which Amur Minerals would play in central role.
Once its definitive feasibility study is completed and the project is financed, Amur envisages a two-year construction period in CY18 and CY19 before first production of nickel in CY20. Produced to meet Russian and western standards, an appropriate permanent TEO could, in turn, lend the project naturally to Russian project finance, in which case management has suggested that an 80:20 debt:equity financing structure could be achievable. However, it is understood that Amur is also investigating the potential to access funding via a streaming arrangement relating to its by-products, in particular. Streaming is associated with less risk than debt (and is not considered as debt by lending banks), as it has neither a fixed repayment schedule nor associated debt-service covenants.
In the meantime, management continues to work on improving the operational blueprint published in June 2015 (and which built on the earlier, conceptual open-pit study). Currently, it envisages that Maly Kurumkon-Flangovy, Ikenskoe-Sobolevsky and Kubuk will support both underground and open-pit mining operations and that Vodorazdelny will support open-pit mining operations alone. In addition, it believes that it has identified a potential c US$150m in capex savings, which could then be used to invest in a flash smelter (vs the electric furnace smelter and converter smelter configuration envisaged).