WPM provided detailed production guidance for FY24 and beyond on 20 February. This guidance is summarised below relative to our updated FY24 forecasts in light of the Q1 and Q2 results:
Exhibit 9: WPM precious metals production – Edison forecasts cf guidance
|
FY24e |
FY28e (target)* |
FY29–33 (average)* |
Prior Edison forecast |
|
|
|
Silver production (Moz) |
19.9 |
|
|
Gold production (koz) |
348.4 |
|
|
Cobalt production (klb) |
882 |
|
|
Palladium production (koz) |
17.1 |
|
|
Gold equivalent (koz) |
591.6 |
816 |
849 |
Current Edison forecast |
|
|
|
Silver production (Moz) |
20.3 |
|
|
Gold production (koz) |
350.3 |
|
|
Cobalt production (klb) |
927 |
|
|
Palladium production (koz) |
17.2 |
|
|
Gold equivalent (koz) |
598.7 |
816 |
849 |
|
|
|
|
WPM guidance |
|
|
|
Silver production (Moz) |
18.5–20.5 |
|
|
Gold production (koz) |
325–370 |
|
|
Cobalt & palladium production (koz AuE) |
12–15 |
|
|
Gold equivalent (koz) |
550–620 |
>800 |
>850 |
Source: Wheaton Precious Metals, Edison Investment Research forecasts. Note: *Edison forecasts include Antamina extension from FY28.
In formulating our forecasts, we are assuming that production will commence at Goose, Platreef and Blackwater in late FY24 or early FY25, to be followed by production from Curipamba and Marathon in FY26, Curraghinalt, Kudz ze Kayah (KZK) and Santo Domingo in FY27 and Cangrejos in FY29.
A brief summary of recent developments at WPM’s principal near-term development projects is as follows:
■
Blackwater: on 30 July, Artemis announced that overall construction of the Blackwater project was 87% complete (as of 30 June), with c C$650m out of a total capital budget of C$730–750m expended, and that it is on schedule for its first gold pour in Q424. A recent evacuation order owing to wildfires in the area of the mine has been lifted and the construction team has now returned to site to ramp up to full-scale operations once again. During Q224, construction and commissioning of the initial phase of the mining fleet was completed, with two 400t hydraulic backhoe excavators, nine 240t rigid frame haul trucks and two large mining front-end loaders now fully assembled. The fleet to support initial operations is therefore now complete. However, additional units are also on site and are in the process of being assembled, with the intention of adding these to the fleet as operations ramp up in due course.
■
Platreef: on 31 July, Ivanhoe announced that construction of Platreef’s Phase 1 concentrator had been completed on schedule after the quarter’s end and that cold commissioning had started, with water being fed through the concentrator. The concentrator will now be placed on care and maintenance until H225, as Shaft 1 prioritises the hoisting of waste from the development required to bring forward the start of Phase 2. In the meantime, work is continuing on the updated feasibility study to accelerate Platreef’s Phase 2, as well as the preliminary economic assessment of the new Phase 3 expansion to take processing capacity to 10Mtpa (2.5x the processing capacity of the Phase 2 expansion), with both studies expected to be completed in Q424. To that end, construction of Platreef’s Shaft 2 headgear – which will take total hoisting capacity for ore and waste development across all three shafts to over 12Mtpa – is now c 60% complete. Simultaneously, construction activities are advancing on the installation of 1,124t of internal structural steel inside Shaft 2’s headgear as well as the installation of the sinking winders and related infrastructure, with the on-boarding of the contractor designated to commence sinking operations in Q125, after which production will begin to ramp up.
■
Goose project: on 7 May, B2Gold announced the successful completion of the 2024 winter ice road campaign, delivering all necessary materials to complete the construction of the Goose project. While mill construction remained on schedule, development of the open pit and underground was slightly behind owing to equipment availability, adverse weather conditions and the prioritisation of critical path construction activities, such that the project’s first gold pour is now expected in Q225 with ramp-up to full production in Q325.
■
Marmato: as at the end of May 2024, Aris reported that it had disbursed US$30m out of its US$280m construction budget for the Lower Mine (ie 10.7%). As such, the Lower Mine project is reported to be on track for first gold pour by end 2025, followed by an approximate six-month ramp-up period. Simultaneously, it reported that it is transforming the Upper Mine production plan by transitioning the operation to contract mining partners, thereby mirroring its operating model at Segovia.
■
Curipamba: on 6 August, Silvercorp announced that the Ecuadorian Ministry of Energy and Mines had issued a Resolution of Change of Phase for the El Domo-Curipamba project, which allows it to advance its legal status from one of ‘economic evaluation’ to ‘exploitation’ and allows for the start of construction and subsequent operation of the mine. This change, for a medium-scale project such as El Domo-Curipamba, is equivalent to an exploitation agreement for large-scale mines in Ecuador such as Fruta del Norte and Mirador and is the final, major approval required for the start of full-scale construction.
■
Fenix: on 8 April, Rio2 announced that its Chilean subsidiary had received the formal Environmental Qualification Resolution for the Fenix gold project, which now allows it to advance permitting activities. There are four principal sectorial permits required before construction can commence, namely 1) Mining Methods, 2) Process Plant, 3) Waste Dumps & Stockpiles and 4) Closure Plan, and work on all of these is reported to be ‘well underway’.
■
Cangrejos: on 21 May, Lumina Gold announced that work on its feasibility study is progressing on schedule and that it expects to have it finalised in Q225. In the meantime, recommendations from the ongoing work and trade-off studies to date include 1) increasing the initial processing plant throughput to 40,000tpd (cf 30,000tpd in the 2023 pre-feasibility study), 2) resequencing the mine plan to mine out the higher-grade Cangrejos deposit first, before commencing mining at Gran Bestia, 3) placing over 300Mt of waste rock back into the Cangrejos pit once mining is complete, thereby significantly reducing the land area required for waste rock storage as well as reducing waste rock haul distances, 4) relocating the waste rock storage facility to land already owned by Lumina, which has the additional benefit of increasing the distance between the project and the nearest communities and 5) re-routing access roads to avoid local population centres. This follows the signing in March of a joint declaration with the Government of Ecuador in preparation for the execution of the extension to the existing Exploration Investment Protection Agreement and Complementary Investment Protection Agreement related to the future construction of the project. In the meantime, Lumina is in the process of engaging an Ecuadorian government-approved environmental and social impact assessment consultant to begin the normal course permitting process, which it expects to take approximately 18 months to complete.
■
Curraghinalt: a public inquiry into the Curraghinalt project was to have begun in September and was expected to last up to six weeks. Subsequent to the first quarter, however, the Planning Appeals Commission and Water Appeals Commission in Northern Ireland concluded that the water abstraction and impoundment licences relative to the project have been rescinded and that licence applications would need to be resubmitted and subsequent public inquiry referrals held. The commission noted that it had suspended arrangements for the current inquiry timetable until it was in receipt of the expected applications, at which time it will move to set directions and new dates for the submission of statements of case and rebuttals and for the opening of the re-scheduled hearing sessions in due course.
■
Marathon: on 31 July, Generation Mining reported that the federal government has approved amendments to Schedule 2 of the Metal and Diamond Mining Effluent Regulations, which will allow for the construction of specific water management structures and operation of key infrastructure for the Marathon project. Generation Mining also states that receipt of the few remaining provincial and federal approvals and permits required for construction is expected within the next few months. On 7 August, it further announced a key milestone with the receipt of the Fisheries Act Authorization (FAA) for the Marathon project. The FAA, issued by Fisheries and Oceans Canada, approves Generation’s plan to avoid, mitigate and offset impacts to fish and fish habitat related to the development of the project. This authorisation represents the final federal approval required to commence construction of the tailings storage facility and water management structures. The project now requires only three remaining provincial approvals to be issued by the Ministry of the Environment, Conservation and Parks and the Ministry of Natural Resources. These are expected in the coming months, following which the Marathon project will have all of the key government permits and approvals required for construction to proceed.
■
Santo Domingo: On 31 July, Capstone Copper published the results of an updated feasibility study for the Santo Domingo project, outlining an optimised mine plan and updated capital and operating cost estimates over a 19-year mine life supported by higher mineral reserve estimates. The report indicates that total gold production is expected to average 35,000oz pa for the first seven years of production (cf 30,000oz pa in the 2020 feasibility study), and 22,000oz pa for the life of mine (cf 17,000oz pa). Capstone has reported that with construction completed at Mantoverde 35km north-east of the Santo Domingo project, it plans to advance several value-enhancing initiatives within the Mantoverde-Santo Domingo district that are yet to be included in the 2024 feasibility study. The first of these is a newly announced two-year, US$25m exploration programme at Mantoverde aimed at supporting the two future processing centres between Mantoverde and Santo Domingo.
■
KZK: the pre-feasibility study for the KZK project in the Yukon was based on an ore reserve of 15.7Mt at 1.3g/t Au, 138g/t Ag, 0.9% Cu, 5.8% Zn and 1.7% Pb and posited mining via both open cut (89%) and underground (11%) methods, with ore processed into separate copper, high precious metal (HPM) and zinc concentrates via sequential flotation through a nominal 2.0Mtpa processing plant to produce c 200,000t of dry zinc concentrate, 60,000t of dry copper concentrate and 50,000t of dry HPM concentrate pa over 10 years, containing c 107ktpa Zn, 14ktpa Cu, 25ktpa Pb, 57koz pa Au and 7.8Moz pa Ag at steady state. In June 2022, following a thorough five-year environmental assessment under the Yukon Environmental and Socio-economic assessment Act, the operator, BMC, received a positive decision document from the Canadian and Yukon governments approving the project to proceed to the licensing regulatory phase. This approval was reaffirmed in a modified decision document issued by the Canadian and Yukon governments in March 2024, following additional consultation with Ross River Dena Council, and applications for the Quartz Mining Licence and the Water Licence, which are required for the project’s development and operation, were submitted to regulatory bodies in August 2022.
WPM’s guidance for FY24 and beyond is based on standardised pricing assumptions of US$2,000/oz gold, US$23.00/oz silver, US$1,000/oz palladium, US$1,000/oz platinum and US$13.00/lb cobalt. Of note is the implied gold/silver ratio of 87.0x, which compares with the current ratio of 88.9x, but a longer-term average of 60.1x since gold was demonetised in August 1971. At the updated standardised prices indicated, our production forecast of 598.7koz gold equivalent (AuE) for FY24 is towards the upper end of WPM’s guidance range of 550–620koz AuE, although our gold equivalent sales forecast of 542.7koz is more conservative (see Exhibit 10).
Otherwise, readers will note that our longer-term production forecasts are very close to WPM’s guidance for the period FY29–33. However, at the moment, these exclude any contribution from either Kutcho or Fenix (together capable of adding c 29k GEOs to production) or Toroparu or WPM’s royalty interests. Note that both our estimates, and WPM’s, necessarily exclude potential future stream acquisitions (of which we expect there to be a number, given the time horizon involved).