Since our last note on the company, on 14 November, Pan African has advised the market of the completion of the Tennant Consolidated (TCGM) acquisition and provided a production update for its operations for H125 plus guidance for FY25 and FY26.
■
Gold production for H125 is expected to be in line with production in H224 (87,581oz). In detail:
•
Following successful plant commissioning and first gold pour in early October, production from the Mogale Tailings Retreatment (MTR) operation of c 9,000oz in H125 has offset a decline in production at Evander owing to a delay in commissioning the subvertical shaft (now resolved). Moreover, the plant’s upfront construction capital is now estimated at ZAR2.35–2.40bn (US$132–135m at prevailing forex rates) cf the ZAR2.50bn (US$141m) originally budgeted, a saving of c ZAR100–150m (US$6–8m). To date, production ramp-up is reported to be ahead of schedule with steady-state production anticipated this month. Production for FY25 is estimated by management to be 33,000oz at an all-in sustaining cost (AISC) of under US$1,000/oz. In the meantime, studies are underway to increase annual production from 50,000oz to 60,000oz pa via:
•
The installation of additional reactors to further improve recoveries.
•
The addition of two carbon-in-leach (CIL) tanks to increase throughput from 800ktpm to 1Mtpm, at a limited estimated capital cost of ZAR70m (US$3.9m).
•
The inclusion of a hard rock crushing circuit to enable the processing of nearby remnant hard rock sources (for which a pre-feasibility study is expected in the next three months).
•
Simultaneously, a feasibility study is to be completed on the Soweto Cluster by September 2025, focusing on the possibility of constructing a new processing facility in closer proximity to the Soweto Cluster tailings storage facilities (TSFs), which would be a stand-alone operation also producing c 50,000oz pa plus the option to include additional proximal TSF resources that will add to the project’s life.
•
Elikhulu is forecast to produce c 26,000oz in H125 and 52,000oz in FY25, after Phases 3 and 4 of the new tailings dam construction were completed ahead of schedule and under budget.
•
The Barberton Tailings Retreatment Plant (BTRP) is on track to produce 7,000–8,000oz in H125.
•
Evander Mines’ underground production ramp-up delays from 24 to 25 Level operations at 8 Shaft have been resolved after the commissioning of the sub-vertical hoisting shaft in December, enabling its full 700t/day hoisting capacity to be achieved. A production loss of 7,000oz for the year is now anticipated by management (cf 5,000oz previously), resulting in a production expectation of c 12,000oz in H125 and 38,000oz in FY25 after the establishment of the 24 Level B-Line raise in Q325, which will further improve face length and mining flexibility and contribute to an improvement in the average grade expected from 6.0g/t to 7.5g/t. Simultaneously, following the dewatering of Evander Mines’ 7 Shaft, long-inclined borehole, reserve delineation drilling at 19 Level at Egoli has commenced to further define the ore payshoot.
•
Multiple Eskom transformer failures at Barberton Mines’ (BGMO’s) Fairview and Sheba operations negatively affected production for 10 days in November (by approximately 2,250oz), with the Eskom power utility’s back-up units also failing as a result of ageing infrastructure. Further contingencies are being implemented to prevent the failures from recurring, with additional spare transformers to be kept on site in the future. As a result, production from BGMO is expected to be c 32,000oz in H125 (cf 34,690oz in H224). However, high-grade areas of the 262 Platform at Fairview Mine, indicated by drill intersections of up to 80g/t Au, are anticipated to be accessed by Q325 as development rates are accelerated, while underground sampling at Consort has confirmed high-grade mineral reserve areas below 41 Level in the Prince Consort (PC) shaft area. Rehabilitation work on the shaft has now been largely completed, allowing operations to recommence. FY25 production is therefore anticipated to be c 73,000oz (cf 71,470oz in FY24).
•
Construction work at TCMG’s Nobles project is proceeding on schedule.
■
FY26 production (excluding TCMG) is expected to increase significantly to c 235–250koz (note that this is exactly in line with our prior expectation, which remains unchanged).
As a result of Pan African’s updated guidance, Edison has revised its production forecasts for the group to those shown in Exhibit 1, below.
Exhibit 1: Pan African production, H121–FY26e (oz)
Operation |
H121 |
H221 |
H122 |
H222 |
H123 |
H223 |
H124 |
H224 |
H125e |
H225e |
FY25e (current) |
FY25e (prior) |
FY26e |
Barberton UG |
42,350 |
42,476 |
39,991 |
35,747 |
32,022 |
32,564 |
36,780 |
34,690 |
32,000 |
41,463 |
73,463 |
79,235 |
80,000 |
BTRP |
10,004 |
8,235 |
9,126 |
10,434 |
10,012 |
9,863 |
9,864 |
9,024 |
7.500 |
7,500 |
15,000 |
13,913 |
12,754 |
Barberton |
52,354 |
50,711 |
49,117 |
46,181 |
42,034 |
42,427 |
46,644 |
43,714 |
39,500 |
48,963 |
88,463 |
93,148 |
92,754 |
Evander UG |
12,607 |
23,409 |
27,312 |
21,538 |
19,173 |
10,359 |
21,307 |
16,978 |
12,000 |
26,000 |
38,000 |
42,042 |
51,921 |
Evander surface |
6,560 |
4,677 |
5,756 |
3,564 |
5,270 |
5,373 |
2,401 |
183 |
0 |
0 |
0 |
0 |
0 |
Evander |
19,169 |
28,086 |
33,068 |
25,102 |
24,443 |
15,732 |
23,708 |
17,161 |
12,000 |
26,000 |
38,000 |
42,042 |
51,921 |
Elikhulu |
26,863 |
24,596 |
25,900 |
26,320 |
25,830 |
24,743 |
28,106 |
26,706 |
26,000 |
26,000 |
52,000 |
49,143 |
46,857 |
MTR |
|
|
|
|
|
|
|
|
9,000 |
24,127 |
33,127 |
24,127 |
54,603 |
Total (excl TCMG) |
98,386 |
103,391 |
108,085 |
97,603 |
92,307 |
82,902 |
98,458 |
87,581 |
86,500 |
125,090 |
211,590 |
208,460 |
246,135 |
Nobles |
|
|
|
|
|
|
|
|
|
|
|
|
62,200 |
Total |
|
|
|
|
|
|
|
|
|
|
|
|
308,335 |
Source: Edison Investment Research, Pan African Resources. Note: Totals may not add up owing to rounding. UG, underground. BTRP, Barberton Tailings Retreatment Project.
Overall, therefore, Edison has increased its (albeit conservative) FY25 production forecast by 3,130oz (1.5%), with all of the increase effectively being accounted for by the seamless commissioning and ramp-up of the MTR project.
In addition to changes to our immediate output assumptions, we have revised our estimate of the gold price for the remainder of the financial year to June up to US$2,682/oz (ie that prevailing at the time of writing). At the same time, we have adjusted our foreign exchange rates to reflect the renewed strength of the rand against both the US dollar and sterling:
■
from ZAR23.1595/£ to ZAR22.5670/£ (-2.6%),
■
from ZAR18.2858/US$ to ZAR17.7435/US$ (-3.0%), and
■
from US$1.2669/£ to US$1.2718/£ (+0.4%).
All told, however, the net effect of these changes on our financial forecasts for FY25 and FY26 has been modest, as shown in Exhibit 2, below:
Exhibit 2: Pan African P&L statement by half year (H123–H224e)
US$000s*
|
H123 |
H223 |
H124 |
H224 |
H125e |
FY25e (current) |
FY25e (prior) |
FY26e (current) |
FY26e (prior) |
Revenue |
156,489 |
165,117 |
193,947 |
179,849 |
206,450 |
485,428 |
459,333 |
596,265 |
597,749 |
Cost of production |
(99,282) |
(99,508) |
(110,292) |
(110,891) |
(111,679) |
(249,739) |
(216,483) |
(321,602) |
(316,974) |
Depreciation |
(11,122) |
(9,277) |
(10,768) |
(10,476) |
(11,539) |
(25,726) |
(38,058) |
(59,432) |
(58,348) |
Mining profit |
46,085 |
56,332 |
72,887 |
58,482 |
83,232 |
209,963 |
204,792 |
215,232 |
222,428 |
Other income/(expenses) |
(3,610) |
(3,737) |
(7,231) |
(3,144) |
(23,473) |
(32,053) |
(16,257) |
(1,592) |
(1,586) |
Loss in associate etc |
0 |
0 |
0 |
0 |
|
|
|
|
|
Loss on disposals |
0 |
0 |
0 |
0 |
|
|
|
|
|
Impairments |
0 |
0 |
0 |
0 |
|
|
|
|
|
Royalty costs |
(468) |
(495) |
(1,242) |
(445) |
(5,269) |
(4,834) |
(4,890) |
(3,941) |
(4,013) |
Net income before finance |
42,007 |
52,100 |
64,414 |
54,893 |
54,490 |
173,077 |
183,645 |
209,699 |
216,829 |
Finance income |
456 |
683 |
760 |
1,124 |
|
|
|
|
|
Finance costs |
(3,464) |
(6,228) |
(5,594) |
(6,190) |
|
|
|
|
|
Net finance income |
(3,008) |
(5,545) |
(4,834) |
(5,066) |
(8,131) |
(17,619) |
(9,396) |
(12,795) |
(11,319) |
Profit before taxation |
38,999 |
46,555 |
59,580 |
49,827 |
46,359 |
155,458 |
174,248 |
196,904 |
205,510 |
Taxation |
(10,063) |
(14,754) |
(17,223) |
(13,358) |
(13,224) |
(49,750) |
(45,769) |
(51,111) |
(53,706) |
Effective tax rate (%) |
25.8 |
31.7 |
28.9 |
26.8 |
28.5 |
32.0 |
26.3 |
26.0 |
26.1 |
PAT (continuing ops) |
28,936 |
31,801 |
42,357 |
36,469 |
33,135 |
105,707 |
128,479 |
145,793 |
151,804 |
Minority interest |
(136) |
(266) |
(224) |
(328) |
0 |
0 |
0 |
0 |
0 |
Ditto (%) |
(0.5) |
(0.8) |
(0.5) |
(0.9) |
0 |
0 |
0 |
0 |
0 |
Attributable profit |
29,072 |
32,067 |
42,581 |
36,797 |
33,135 |
105,707 |
128,479 |
145,793 |
151,804 |
|
|
|
|
|
|
|
|
|
|
Headline earnings |
29,072 |
31,392 |
42,581 |
36,903 |
33,135 |
105,707 |
128,479 |
145,793 |
151,804 |
Est normalised headline earnings |
32,682 |
35,129 |
49,812 |
40,047 |
56,608 |
137,760 |
144,736 |
147,385 |
153,390 |
|
|
|
|
|
|
|
|
|
|
EPS (c) |
1.52 |
1.67 |
2.22 |
1.92 |
1.63 |
5.21 |
6.29 |
7.18 |
7.43 |
HEPS** (c) |
1.52 |
1.63 |
2.22 |
1.93 |
1.63 |
5.21 |
6.29 |
7.18 |
7.43 |
Normalised HEPS (c) |
1.71 |
1.83 |
2.60 |
2.09 |
2.79 |
6.79 |
7.09 |
7.26 |
7.51 |
Source: Pan African Resources, Edison Investment Research. Note: As reported basis. *Unless otherwise indicated. **HEPS, headline earnings per share (South African company adjusted basis).
Our forecast for mining profit for FY25e has therefore actually risen relative to our prior estimate and the decline in our EPS and HEPS forecasts for FY25e may be largely attributed to the increase in our forecast for the contract liability related to the fixed-price forward sales associated with Pan African’s ZAR400m Mintails financing facility, which, readers will recall, Edison shows in the ‘Other income/(expenses)’ line of the profit & loss statement. Although this is not in accordance with accounting standards, it allows the underlying performance of the operating company to be distinguished from the volatility created by derivative-type profits and losses, which would otherwise be more strictly included in the revenue line. Otherwise, the 4.2% decline in our forecast for normalised EPS is broadly in line with the 3.0% decline in the dollar/rand forex rate since the time of our last note. Readers will also note that Edison’s forecasts for PAF’s royalty costs and its effective tax rate (which are driven by formulae) are high within the historical context and, with respect to these measures, they may therefore be considered conservative. This may be seen in a comparison between Edison and consensus forecasts for the periods in question:
Exhibit 3: Pan African H125, FY25 and FY26 consensus EPS forecasts cf Edison (US cents per share)
|
H125 |
FY25 |
FY26 |
Edison forecasts |
2.79 |
6.79 |
7.26 |
Mean consensus |
3.00 |
7.60 |
10.8 |
High consensus |
3.00 |
9.00 |
14.5 |
Low consensus |
3.00 |
6.00 |
6.00 |
Source: LSEG Data & Analytics, Edison Investment Research. Note: As at 12 December 2024.
In the light of these developments, we are continuing to forecast that group production from FY26 onwards will easily exceed 250koz per year with a material contribution from TCGM’s assets and may approach 400koz pa in FY29, when all of PAF’s mines are operating at close to capacity, pushing normalised headline EPS (HEPS) as high as 9c per share (see Exhibit 5).
Exhibit 4: Estimated Pan African group gold production profile, FY18–30e
|
|
Source: Edison Investment Research, Pan African Resources
|