Electricity business positioning improved
JEL posted a further improvement in profitability in FY15 due to lower electricity supply costs and additional returns on newly commissioned assets. Increased interconnector capacity facilitated the use of cheaper imported electricity, allowing returns to rise, while holding tariffs at a discount to European levels and reducing the carbon intensity of the business. Thanks to the substantial investment programme of recent years, JEL is now well positioned to continue to earn normalised returns for shareholders after the trough years of FY12 and FY13.
Strong performance in FY15
The FY15 results demonstrated a further rise in profitability, with operating profits +39% versus FY14 (before £0.8m of exceptional items). The improvement was, in large part, due to a rise in operating profitability in the core Energy business (FY15 £11.5 m vs FY14 £8.0m). Boosting core profitability was a fall in electricity purchase costs (-£3.9m), thanks to an increased use of cheaper imported electricity (94% in FY15 vs 80% in FY14) and the additional return earned on the enlarged asset base. Greater use of the interconnectors also allowed JEL to reduce the carbon intensity of the power it distributes to an all-time low of 33g CO2e/kWh. Although the Building Services business continued to record small losses (<£0.1m), due to competitive pressures, the retail business reaped the benefit of the previous year’s restructuring, converting an operating loss of £0.1m in FY14 into an operating profit of £0.3m in FY15. Thanks mainly to the benefit of higher occupancy levels, the property business recorded a further rise in profitability from £1.4m to £1.6m. Capex, which had been boosted by expenditure on the N3 interconnector, fell significantly (49.1%) versus FY14. Lower capex, combined with improved profitability, allowed for improved cash flow, with net debt falling from £20.2m to £17.5m. JEL remains modestly geared, with net debt/equity at c 12%.
Exhibit 2: JEL evolution of key operating metrics – 2015 versus 2014
|
|
2014 |
2015 |
% |
Turnover |
£m |
98.4 |
100.5 |
+2.1% |
Operating profit (before exceptional items and intangible amortisation) |
£m |
10.0 |
13.9 |
+39.0% |
PBT |
£m |
6.5 |
13.2 |
+103.1% |
EPS (After exceptional items) |
p |
16.1 |
35.0 |
+117.4% |
DPS |
p |
12.20 |
12.85 |
+5.3% |
Net (debt)/cash (incl prefs & debt) |
£m |
(20.2) |
(17.5) |
-13.4% |
Capex |
£m |
(33.1) |
(16.8) |
-49.1% |
Source: Jersey Electricity
Jersey energy market – market trends
Demand growth over the last 15 years has been modest (CAGR of c 0.8% over the period 2000-15). A secular move to energy efficiency (more efficient appliances/lighting) and JEL’s strategy of encouraging the use of high-efficiency, lower-cost off-peak heating has helped restrain overall demand growth and moderate the growth in peak demand. The 2015 maximum demand figure of 148MW shows that there has been little growth in peak demand since 2005 (2005-15 CAGR 0.4%). JEL’s policy of seeking to flatten the load curve has helped to limit infrastructure costs and keep prices to customers lower than would otherwise have been the case. We believe the outlook for demand growth is likely to remain modest and, with the scheduled commissioning of N1 in Q117, we expect JEL to be able to satisfy incremental demand via imports from France.
Jersey energy market – regulation
Electricity Law and Competition Law exist to govern corporate behaviour, but JEL continues to operate as a self-regulated business. JEL aims to earn a 6-7% return (pre-tax) on its energy assets (net of customer contributions and working capital adjustments) on a rolling five-year basis. In extreme circumstances, such as with the interconnector failures of 2012, unexpected costs may arise that cannot be recovered through the tariff setting process, leading to sub-target returns for the year. Equally, in some years (such as in FY15), returns may rise above the upper end of the targeted range.
Exhibit 3: JEL – total electricity supplied and evolution of peak demand
|
|
Source: Jersey Electricity, Edison Investment Research
|
JEL also aims to ensure that tariffs remain within ±10% of the EU-15 average once all taxes are included. Currently, JEL’s general domestic tariff is 14.5p/kWh including the goods and services tax (GST). At an exchange rate of €0.72/£, JEL’s tariffs translate to a price of €0.201/kWh. Eurostat data show that the average EU-15 domestic tariff in H115 was €0.215/kWh, leaving JEL’s prices at a c 6% discount to the EU average. In broad terms, this accords with JEL’s own study, which shows prices at a 5% discount.
Exhibit 4: EU-15 electricity prices for domestic consumers H115 (€ per kilowatt hour)
|
|
|
There appears to be little appetite to change the regulatory framework. In December 2012 CICRA published a review of the electricity market in Jersey, which found that JEL earned a return on its assets comparable to the UK utilities and offered a reasonable level of service to its customers. The report also found that the risk of inefficiencies appeared low and concluded that it was not minded to recommend modification to the existing regime. In addition, a recent review of the Jersey regulatory and competition framework prepared by Oxera for the Government of Jersey concluded that “in some parts of the economy the role of the regulator is essentially taken on by the government, and, in many cases, the regulatory cost is (or at least appears to be) relatively low. Although a full analysis of the approach of government as ‘regulator’ is outside the scope of this review, it is noticeable that one element of this approach appears to be a much simpler regulatory system”. In our view, sub-peer group tariffs, high levels of system reliability and a simple low-cost system of regulation reduce the likelihood of regulatory change.
JEL’s strategy is focused on continuing to grow its share of the Jersey energy market by replacing other sources of energy. In pursuit of its strategic objectives, JEL seeks to ensure high levels of network reliability (minimising customer minutes lost) and affordability of supply for its customers by sourcing cheaper off-island electricity (no tariff rises in 2015), and, by building a relationship with the customer, to embrace other aspects of energy provision (maintenance/installation) via its Building Services division. In addition, the import agreements with EdF have enabled JEL to reduce the carbon intensity of the electricity it supplies, making a valuable contribution to the States of Jersey’s long-term carbon reduction targets and allowing it to offer substantially cleaner energy than other on-island sources (heating oil 265g CO2e/kWh, LPG 234g CO2e/kWh). JEL’s strategy appears to be bearing fruit, with the third successive year of improved customer service ratings according to its annual survey. Co-operative agreements with Guernsey Electricity also form part of its strategy, as for example in the case of the N3 interconnector, but JEL currently has no ambitions to extend its reach beyond the Channel Islands. In the event that renewable investment grows in importance on the island, JEL will seek to provide the required infrastructure to facilitate the proposed investment rather than invest directly itself, as it believes the risks associated with large offshore investment are too great for a utility of its scale.
JEL: Asset base and capex
JEL’s gross asset base of the energy business of c £191m has been growing at a CAGR of c 7% over the last 10 years. Gross energy assets differ from JEL’s regulatory asset base, which deducts customer contributions and working capital items. Since 2005 depreciation has averaged c £7.1m pa compared to capital expenditure of c £14.8m. For the early part of the period 2005-10, depreciation and capex were more closely aligned (capex £8.6m/depreciation £6.6m), although post-2012 capex rose sharply, in large part due to heavy expenditure on a new interconnector with France (N3 total project cost £70m), but also reflecting the repair of the connection with Guernsey, on-island network refurbishment and the installation of two 11MW diesel gensets.
Exhibit 5: JEL – energy business capex, depreciation and gross asset base (2005-15)
|
|
Source: Jersey Electricity, Edison Investment Research
|
Future capex is likely to be focused on two areas: the installation of additional interconnector capacity with France (N1, £40m – 30% payable by Guernsey Electricity) and the construction of a new primary substation (£17m) to reinforce the on-island network. The N1 interconnector will replace the original EdF1 (55MW) interconnector, which failed in 2012. The old cable (EdF1) is scheduled for removal in the spring, with the surface lay of the new cable anticipated for summer 2016, and commissioning possible in Q117. JEL has also acquired a site from the Parish of St Helier for a new 90kV primary substation (granted planning permission in May 2014). Groundworks have started and commissioning is scheduled for 2018. We also expect JEL to continue to roll out its smart metering programme. We expect capex to return to relatively high levels in FY16 due to forecast expenditure in N1 and the substation. In FY17 we expect expenditure to decline to c £16m. Beyond 2017 we expect that capex will return to normalised levels of £10-15m pa.
The main plank of Jersey Electricity’s strategy for ensuring continuity of power supply has been to focus on maintaining and expanding the interconnectors with France, particularly after the failures that occurred in the summer of 2012. We expect this strategy to enable Jersey to import c 95% of its electricity in the future (similar to the level achieved in FY15). However, to meet its security of supply standards, JEL maintains its on-island generation capacity. Although some uneconomic and inflexible capacity at La Collette was decommissioned during the year, during 2016 JEL is installing a ‘black start’ diesel generator (5.5MW) at La Collette and £12m was spent in 2012 on a project to install two 11MW diesel gensets (now four in total). The remaining capacity at La Collette, taken together with the fast-start capacity at Queens Road and the States of Jersey’s EfW plant, mean that on-island capacity exceeds the island’s all-time peak demand of 161MW. Given the additional interconnector capacity scheduled to be commissioned in 2016/17, we do not expect significant expenditure on generating capacity in the near term.
Exhibit 6: Jersey Electricity – percentage of imported electricity 2007-15
|
2006/07 |
2007/08 |
2008/09 |
2009/10 |
2010/11 |
2011/12 |
2012/13 |
2013/14 |
2014/15 |
% of units imported |
88.7 |
96.3 |
92.3 |
93.5 |
95.6 |
92.1 |
75.4 |
80.2 |
94.0 |
Source: Jersey Electricity
Interconnectors remain critical to the profitability and carbon intensity of JEL’s business, but no less important in ensuring the reliability and affordability of electricity supply. As part of its infrastructure plan, JEL aims to deliver three submarine cables between Jersey and France. The significance of the interconnectors was underlined by the impact of the N3 cable on the FY15 results. The new 32km Normandie 3 (N3) interconnector (100MW) first began importing power in September 2014, entering service ahead of schedule and below budget at around £60m (project total shared with Guernsey Electricity). The new interconnector follows a different route and is connected to a different part of the French network to the existing N2 interconnector, enhancing security of supply beyond the headline additional capacity. In February 2015 JEL also supported Guernsey Electricity in a pre-emptive repair to the Jersey-Guernsey link (GJI).
In the summer of 2015, JEL signed a contract for a third power cable link (100MW) with France, known as Normandie 1 (N1). N1 is designed as a direct replacement for EdF1 (55MW, 1984), which failed in 2012. N1 is also a Channel Islands Electricity Grid (CIEG) project and is expected to cost £40m in total. The project, on a £/MW basis, is significantly cheaper than N3, helped by the fact that N1 will follow the same route as EdF1, minimising the need for additional infrastructure. In addition, the cable will be laid on the surface of the seabed (rather than buried like N3), reducing installation time. It is expected that the existing cable will be removed in the spring of 2016, with new cable laying occurring in the summer. JEL anticipates full commissioning of N1 in Q117.
JEL operates a transmission (90kV) and distribution network (>33kV) of c 1,600km (90% underground). The network is well maintained and enjoys high levels of availability and low levels of customer minutes lost (7 minutes in FY15 c 10x better than the UK average), an important service indicator for JEL. Independent research into energy security on islands concluded that, of the 25 jurisdictions studied, JEL was placed in the top four for security of supply. 2012 and 2014 were exceptions to the high level of network reliability, although a large proportion of the total minutes lost can be attributed to problems with interconnectors. In 2012 the failure of EdF1 and EdF2 dominated, while in 2014 (January) a lightning strike in France severed supplies to the sole operational interconnector and accounted for 97 of the 110 minutes lost. JEL continues to invest in strengthening the resilience of the distribution network (around 34km of new cable and 6MVA of new transformer capacity in FY15) and will invest in a new primary substation in St Helier over the next two to three years.
Exhibit 7: JEL – Customer minutes lost (2007-15)
|
2007 |
2008 |
2009 |
2010 |
2011 |
2012 |
2013 |
2014 |
2015 |
Customer minutes lost |
59 |
5 |
9 |
10 |
45 |
293 |
13 |
110 |
7 |
Source: Jersey Electricity, Edison Investment Research
Jersey has a target of reducing carbon emissions by 80% by 2050 (compared to 1990). Jersey has made progress in reducing CO2e emissions, in large part due to JEL’s supply agreement with EdF, which guarantees power from low carbon sources (nuclear 65%, hydro 35%). In FY15 JEL achieved its lowest ever annual carbon intensity – 33g CO2e/kWh – more than 10 times cleaner than the UK electricity system. While carbon intensity has been reduced, little has been done to encourage investment in renewable energy despite significant indigenous renewable resources (wind/tidal/solar). Although the States of Jersey Energy Plan’s (2012) key objective was to “introduce an Energy Policy to move towards a low-carbon economy”, no subsidy or incentive arrangement was established. Given the already low-carbon intensity of electricity supplied on the island, developing a case for a programme of renewable subsidy remains difficult and, as a consequence, investment in on-island renewable generation has been negligible. In the event that either suitable incentive arrangements are provided to encourage large-scale renewable investment, or renewable generation costs become competitive (more difficult at current low commodity prices), JEL would seek to participate through the provision of network services rather than via direct investment in renewable infrastructure. In short, JEL believes it could play an important facilitation role in the introduction of renewable energy to Jersey and thereby develop an opportunity to create value.
Retail: due to the significant restructuring programme (reduced retail floor space, reduction in staff numbers and revised terms and conditions, completed in February 2014) and the enhanced online platform (powerhouse.je), in FY15 JEL achieved a return to profitability in retailing (FY15 £0.3m vs
-£0.1m FY14). However, the market is said to remain challenging, and in our view it is unrealistic to expect a further significant rise in profitability.
Property: the property business generates income from both the residential and commercial market. Residential income is generated from legacy properties, originally built to house staff, while commercial income comes from developments adjacent to JEL’s offices on the Powerhouse Retail Park. Over the last 10 years, the profitability of this business has increased by c 2.5% annually and we expect a similar rate of growth going forward (facilitated by rent reviews).
Building Services: the Building Services division (JEBS) includes the provision of services in the following areas: public lighting, heating installation, air conditioning and maintenance work, and is designed to strengthen JEL’s relationship with the customer “beyond the meter”, as well as helping to build load for the core electricity business. Competitive pressure on margins and the limited scale of the market suggest that JEBS will find it challenging to make a positive contribution to group profits.
Other: other businesses contributed c £0.6m to group profits in FY15 (£0.7m in FY14). Jendev focuses on software development for utilities and generated turnover in excess of £1m in FY15. JEL envisages a period of sustainable revenue for the business and Jendev is currently exploring commercial opportunities with partners. Jersey Energy provides environmental and building services expertise for developers and architects and continues to perform satisfactorily, achieving revenue of £0.5m in FY15, with profits said to be “ahead of expectations”.