KEFI Minerals — Update 30 September 2015

KEFI Gold and Copper (AIM: KEFI)

Last close As at 23/11/2024

GBP0.01

0.03 (5.08%)

Market capitalisation

GBP36m

More on this equity

Research: Metals & Mining

KEFI Minerals — Update 30 September 2015

KEFI Minerals

Lord Ashbourne

Written by

Lord Ashbourne

Director of Content, Mining

Metals & Mining

KEFI Minerals

More gold faster and cheaper

H1 results & DFS evolution

Metals & mining

1 October 2015

Price

0.53p

Market cap

£9m

US$1.5231/£

Net cash (£m) at 30 June 2015

1.0

Shares in issue

1,744.4m

Free float

89.5%

Code

KEFI

Primary exchange

AIM

Secondary exchange

N/A

Share price performance

%

1m

3m

12m

Abs

(33.3)

(39.4)

(63.6)

Rel (local)

(31.4)

(35.1)

(61.5)

52-week high/low

1.3p

0.5p

Business description

KEFI Minerals is an exploration and development company focused on gold and copper deposits in the highly prospective Arabian-Nubian Shield – principally the 95%-owned Tulu Kapi project in Ethiopia and, to a lesser extent, the 40%-owned Jibal Qutman project in Saudi Arabia.

Next events

Financing details

Q415

Analyst

Charles Gibson

+44 (0)20 3077 5724

KEFI’s DFS on Tulu Kapi was based on a conventional owner-operator model to estimate costs from first principles (see page 2). However, to minimise initial capex, management then invited final bids from fixed-price plant building and mining contractors. In collaboration with these, it has also been able to announce a 25% expansion of the proposed processing rate to 1.5Mtpa, such that KEFI shares now offer investors an IRR of 38.6% in sterling terms over 12 years (vs 25.9% over 17 years previously). Significantly, KEFI has also confirmed that the Ethiopian government is planning to proceed with a US$20m investment at the project subsidiary level at a valuation related toTulu Kapi’s NPV at the current gold price.

Year end

Revenue (£m)

PBT*
(£m)

EPS*
(p)

DPS
(p)

P/E
(x)

Yield
(%)

12/13

0.0

(0.9)

(0.4)

0.0

N/A

N/A

12/14

0.0

(2.6)

(0.4)

0.0

N/A

N/A

12/15e

0.0

(1.8)

(0.2)

0.0

N/A

N/A

12/16e

0.0

(6.1)

(0.3)

0.0

N/A

N/A

Note: *PBT and EPS are normalised, excluding intangible amortisation and exceptional items.

Reduced capex and opex

In contrast to the original processing plan, the updated schedule seeks to process the same quantity of ore over 11, rather than 14 years (although the mine plan remains unchanged). As a result, there is an increase in forecast gold production in the first nine years of operations. By contrast, while there is an increase in gross costs in six of the first seven years of operations, there is a 3.1% decline overall over the full 11-year life of operations, resulting in a 2.7% decline in unit costs of production (including offsite costs and royalties), from US$761/oz to US$740/oz. In addition to the revised plant throughput schedule, KEFI is in the process of revising and optimising its capex estimates. Relative to estimates at the time of our initiation note in August, KEFI’s latest estimates indicate an 11.1% reduction in upfront capital expenditure (including working capital and community relocation costs).

Valuation: Up 34.2% to 2.59p per share

We calculate that KEFI is capable of generating average after-tax earnings of c £25m pa for eight years, from 2018 to 2025 (vs £20m pa previously) and free cash flow of £34m pa (vs £32m previously). Without taking into account the anticipated streaming deal and using a 10% discount rate, our updated estimate of the project’s NPV is £78.8m (vs £68.0m previously), or 4.5p/share (4.3p attributable) at our long-term gold prices. Whereas previously funding had been assumed to be in the form of a US$100m streaming agreement and a US$10m equity raise, it is now assumed to be in the form of streaming (US$45m), equity in the project (US$20m) and equity in the parent (US$5m), with the balance to be provided in the form of conventional debt. On the basis of these funding assumptions in particular, we now estimate that KEFI investors may expect maximum potential dividends in the order of 0.69p/share pa, which have a value over the life of operations of 2.59p/share in 2015 (using a 10% discount rate), rising to 3.79p/share in FY19.

Investment summary: Updated estimates and forecasts

With collaboration from Senet, Golders, Epoch and Snowden, KEFI completed an updated definitive feasibility study (DFS) on the Tulu Kapi project in July 2015. The DFS reflected both a complete overhaul, and an independent validation, of the Tulu Kapi geological resources and reserves, whereby KEFI inserted significant additional data and “wireframed” each individual ore lode in the system as part of a concerted programme of works to put behind it the issues raised by the intended bankers about the previous project plans under past ownership. Capex for the project in the DFS was estimated to be US$176m. However, the study was completed as if Tulu Kapi would be owner-operated. In consideration of the need to minimise initial capital expenditure, as well as the more exacting technical requirements of the selective mining campaign, KEFI instead decided to pursue a contract mining business plan, with the result that estimates for development capex initially reduced to US$141.2m (including working capital and relocation costs), which formed the basis of our initiation note, published in August 2015.

The development plan for Tulu Kapi has continued to evolve since then and, on 7 September, KEFI announced revised operational parameters for the project, based on an increased plant throughput rate. The expansion was based on the company’s ongoing discussions with potential project contractors. However, whereas the processing rate will increase, the mine plan will remain unchanged, as the original plan envisaged building up a stockpile, which would then be processed in years 11 to 14 of the project. The updated plan, by contrast, assumes a closer relationship between mining and processing rates, such that both are completed in year 11 of the project. However, based on the bids received to date, KEFI does not expect the expanded plant to increase the assumed level of funding required to develop the mine. A summary of the new processing plan and cost schedule is shown in Exhibit 1 below.

Exhibit 1: Updated Tulu Kapi mine plan and cost assumptions

2017e

2018e

2019e

2020e

2021e

2022e

2023e

2024e

2025e

2026e

2027e

2028e

2029e

2030e

Waste (kt)

7,281

12,922

15,446

17,368

16,688

17,091

14,120

7,462

3,728

1,740

353

0

0

0

Stripping ratio

5.2

5.2

6.3

15.3

9.2

12.1

7.3

5.2

4.7

5.2

2.8

0

0

0

Ore processed (kt)

950

1,500

1,500

1,500

1,500

1,500

1,500

1,500

1,500

1,500

943

0

0

0

Grade (g/t)

1.77

2.59

2.88

2.01

2.24

2.26

2.48

2.29

2.13

1.24

0.85

0.00

0.00

0.00

Contained gold (koz)

54.1

124.7

139.0

96.9

107.9

109.1

119.6

110.7

102.6

59.8

25.8

0.0

0.0

0.0

Recovery (%)

92.47

92.82

92.90

92.38

92.55

92.05

90.46

89.61

89.98

89.79

89.67

0.00

0.00

0.00

Recovered gold (koz)

50.0

115.8

129.1

89.5

99.9

100.5

108.2

99.2

92.3

53.7

23.2

0.0

0.0

0.0

Operating costs (US$/t processed unless otherwise indicated)

Mining (US$/t mined)*

3.69

3.09

3.25

3.17

2.97

2.99

3.29

3.08

3.23

3.63

4.76

0.00

0.00

0.00

Milling (oxide, US$/t)

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

Milling (fresh ore, US$/t)

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

Milling (hard ore, US$/t)

0.00

0.00 

0.00 

9.60

9.60

9.60

9.60

9.60

9.60

9.60

9.60

0.00

0.00

0.00

Total (US$/t)

47.90

44.02

50.90

51.22

48.71

49.16

48.32

31.75

22.71

17.97

16.26

0.00

0.00

0.00

Gold price (US$/oz)

1,347

1,408

1,483

1,467

1,409

1,404

1,389

1,379

1,398

1,423

1,431

1,439

1,409

1,395

Sustaining capex (US$000’s)

2,872

5,773

2,787

3,411

2,248

5,816

0

0

0

0

0

0

0

0

Source: KEFI Minerals, Edison Investment Research. Note: *Includes waste.

This may be compared to the assumptions used in our initiation note, which are reproduced in Exhibit 2 below.

Exhibit 2: Previous Tulu Kapi assumptions

2017e

2018e

2019e

2020e

2021e

2022e

2023e

2024e

2025e

2026e

2027e

2028e

2029e

2030e

Ore processed (kt)

800

1,200

1,200

1,200

1,200

1,200

1,200

1,200

1,200

1,200

1,200

1,200

1,200

193

Grade (g/t)

1.95

3.01

3.33

2.27

2.60

2.63

2.91

2.68

2.49

1.64

0.86

0.70

0.70

0.68

Contained gold (koz)

50.2

116.1

128.6

87.7

100.1

101.4

112.2

103.3

95.9

63.4

33.3

26.9

26.9

4.3

Recovery (%)

92.63

92.92

92.97

92.43

92.62

92.08

90.39

89.47

89.88

90.54

90.89

91.41

89.80

88.78

Recovered gold (koz)

46.5

107.9

119.5

81.1

92.7

93.4

101.5

92.4

86.2

57.4

30.2

24.6

24.1

3.8

Operating costs (US$/t processed unless otherwise indicated)

Mining (US$/t mined)*

2.81

3.39

3.66

2.01

2.75

2.94

3.50

4.14

4.67

5.36

4.85

3.00

3.02

9.70

Milling (oxide)

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

9.98

Milling (fresh ore)

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

7.63

Milling (hard ore)

9.60

9.60

9.60

9.60

9.60

9.60

9.60

9.60

9.60

9.60

9.60

9.60

9.60

9.60

Total (US$/t)

43.69

53.59

64.37

44.82

54.60

58.75

59.62

45.25

33.99

27.37

19.01

13.61

15.06

23.92

Gold price (US$/oz)

1,347

1,408

1,483

1,467

1,409

1,404

1,389

1,379

1,398

1,423

1,431

1,439

1,409

1,395

Sustaining capex (US$000’s)

3,054

5,927

2,649

3,350

2,248

800

0

0

0

0

0

0

0

0

Source: KEFI Minerals, Edison Investment Research. Note: *Includes waste.

As previously, additional costs include the 7% mining royalty, US$8.5m in life-of-mine offsite costs and an US$11.9m provision for closure costs. On-site general and administrative costs are forecast to be US$7.1m pa during full mining and processing operations and US$3.6m pa while reprocessing stockpiles (for the final nine months of operations only). Head office costs are assumed to amount to £2.0m pa. A carried-forward tax loss of US$60m has also been applied to future pre-tax profits before tax is payable.

The principal differences between the two plans may be summarised as follows:

the same quantity of ore and waste mined;

the same quantity of ore processed, but processed over 11, rather than 14 years (including part-years);

a decline in the head grade of ore processed in all 11 years;

an increase in gold production in the first nine years of operations, owing to increased plant throughput;

an increase in gross costs (in US$m) in six of the first seven years of operations; however, a 3.1% decline in gross costs over the full 11-year life of operations;

an increase in unit costs (as measured in US$/t processed) in only two of the first seven years of operations on account of higher plant throughput rates; and

a decrease in initial sustaining capital, but a US$4.9m increase over the life of operations.

A summary of these changes is provided in the table below in the units in which each of these parameters is reported.

Exhibit 3: Tulu Kapi mine plan and cost assumption changes

2017e

2018e

2019e

2020e

2021e

2022e

2023e

2024e

2025e

2026e

2027e

2028e

2029e

2030e

Ore processed (kt)

150

300

300

300

300

300

300

300

300

300

-257

-1,200

-1,200

-193

Grade (g/t)

-0.18

-0.42

-0.45

-0.26

-0.36

-0.37

-0.43

-0.39

-0.36

-0.40

-0.01

-0.70

-0.70

-0.68

Contained gold (koz)

3.9

8.6

10.4

9.2

7.8

7.7

7.4

7.4

6.7

-3.6

-7.5

-26.9

-26.9

-4.3

Recovery (%)

-0.16

-0.10

-0.07

-0.05

-0.07

-0.03

0.07

0.14

0.10

-0.75

-1.22

N/A

N/A

N/A

Recovered gold (koz)

3.5

7.9

9.6

8.4

7.2

7.1

6.7

6.8

6.1

-3.7

-7.0

-24.6

-24.1

-3.8

Operating costs (US$/t processed unless otherwise indicated)

Mining (US$/t mined)*

0.88

-0.30

-0.41

1.16

0.22

0.05

-0.21

-1.06

-1.44

-1.73

-0.09

N/A

N/A

N/A

Milling (oxide)

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

N/A

N/A

N/A

Milling (fresh ore)

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

N/A

N/A

N/A

Milling (hard ore)

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

N/A

N/A

N/A

Total (US$/t)

4.21

-9.57

-13.47

6.40

-5.89

-9.59

-11.30

-13.50

-11.28

-9.40

-2.75

N/A

N/A

N/A

Gold price (US$/oz)

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Sustaining capex (US$000’s)

-182

-154

138

61

0

5,016

0

0

0

0

0

0

0

0

Source: KEFI Minerals, Edison Investment Research. Note: *Includes waste.

Overall, unit working costs decline 3.1% under the updated processing schedule (from US$40.77/t processed to US$39.50/t). By contrast, total unit cash costs of production, which include unchanged offsite and royalty cost assumptions, decline 2.7%, from US$761/oz to US$740/oz.

In addition to the revised plant throughput schedule, KEFI is in the process of revising and optimising its capital expenditure estimates. Updated capital cost estimates, including their evolution since the release of the original BFS in July, and projected savings are provided in Exhibit 4 below.

Exhibit 4: Tulu Kapi initial capex estimate evolution, July 2015 to present

Capital expenditure

Original BFS

Original contract mining estimates*

Updated contract mining estimates and savings

Mining

39,742

10,586

15,586

Processing

79,908

72,300

65,614

Infrastructure

21,748

17,800

16,748

Tailings

7,088

8,200

7,088

Indirect (EPCM, contract mining etc)

0

10,800

14,294

Owners Cost

8,854

7,604

7,604

Independent Technical Experts’ (ITE) review

5,717

0

5,717

Working Capital

0

6,100

6,579

Other

12,543

0

13,291

Subtotal

175,600

133,390

152,521

Relocation & livelihood restitution

8,330

7,800

8,330

Total

183,930

141,190

160,851

Deferred payment of EPC contractor

-10,417

Further savings in mining, tailings, access roads etc

-10,448

Targeted savings in civils

-11,478

Further targeted EPC savings offset by expansion costs

-3,000

Total after savings

125,507

Source: KEFI Minerals, Edison Investment Research. Note: *As used in our August 2015 initiation note.

Note that the US$10.4m reduction in the retainer payable to KEFI’s EPC contractor is presumed to be a deferral only, ie it is assumed that a payment for the same amount will occur, but later in the life of the mine’s operations, such that it will not be a part of initial capital expenditure and will therefore be payable out of cash flows, rather than adding to KEFI’s initial funding requirement.

On the basis of these updated estimates, overall, pre-production capex equates to US$1,203 per annual oz of average gold production at full capacity (vs US$1,396 previously), or US$83.67/t of ore processed (vs 112.6/t previously).

Valuation

KEFI has recently announced that it intends to source US$20m in funding for the project “as minority equity investment in the project subsidiary” and that this will “be priced at a valuation reflecting Tulu Kapi’s net present value of c US$100m at current gold prices.” On this basis, a US$20m investment in the project subsidiary would confer a 16.7% interest in the project on the investor and KEFI has confirmed that the government of Ethiopia is now planning to proceed with such an arrangement, which is self-evidently a positive development.

Whereas previously funding had been assumed to be in the form of a US$100m streaming agreement and a US$10m equity raise, it is now assumed to be in the form of streaming (US$45m), equity in the project (US$20m) and equity in the parent (US$5m), with the balance to be provided in the form of conventional debt.

On the basis of the above assumptions alone and converting at the prevailing foreign exchange rate of US$1.5231/£ (vs 1.55/£ previously), we calculate that KEFI is capable of generating average after-tax earnings of c £25m pa for eight years, from 2018 to 2025 (vs £20m pa previously) and free cash flow of £34m pa (vs £32m previously) on a 100% basis. Without taking into account the anticipated streaming deal and using a 10% discount rate, our updated estimate of the project’s NPV is £78.8m (vs £68.0m previously), or 4.5p per existing share (4.3p attributable). The project’s internal rate of return increases from 26.1% to 29.5%.

Over the period since our initiation note, KEFI’s share price has fallen from 0.78p to 0.53p. However, to the extent that this implies a proportionate increase in dilution (although the amount of equity to be raised is now lower), this is more than offset by the fact that dividends will be paid out over a shorter, earlier timespan (notwithstanding the increased minority interest), with the result that investors in KEFI’s shares may expect maximum potential dividends in the order of 0.69p/share pa (vs 0.46p/share previously). Therefore, whereas the net present value of this dividend stream was 1.93p/share previously (when discounted at 10% pa), it is now 2.59p – an increase of 34.2%. This valuation then rises to 3.79p/share (vs 2.82p/share previously) in FY19, being the year of the first (potential) substantive dividend payment. As a result, an investment in KEFI shares at a price of 0.53p per share will therefore generate a return to investors of 38.6% in sterling terms over 12 years (vs 25.9% over 17 years previously).

Exhibit 5: Edison estimate of life-of-mine KEFI EPS and (maximum potential) DPS

Source: Edison Investment Research. Note: DDF = discounted dividend flow.

Sensitivities

Quantitatively, our DDF valuation of 2.59p is most sensitive to the gold price, cash costs and the discount rate, as shown in Exhibits 6 and 7 below.

Exhibit 6: Discounted dividend valuation sensitivity to gold prices and costs

Valuation (pence per share)

Gold price

Spot price*

-20%

-10%

Base case

+10%

+20%

+20%

0.00

0.00

0.45

1.35

2.29

3.23

+10%

0.10

0.14

1.03

1.97

2.91

3.85

Cash costs

Base case

0.68

0.72

1.64

2.59

3.53

4.48

-10%

1.27

1.32

2.26

3.21

4.16

5.11

-20%

1.88

1.93

2.88

3.83

4.79

5.75

Source: Edison Investment Research. Note: *US$1,128/oz.

A 10% change in the gold price from our long-term forecasts therefore results in a c 0.94p per share change in our KEFI valuation, whereas a 10% change in cash costs (excluding royalty and offsite costs) results in a 0.62p per share change.

Exhibit 7: Discounted dividend valuation relative to discount rate

Discount rate (%)

0%

5%

10%

15%

20%

25%

30%

Valuation (pence)

6.21

3.94

2.59

1.75

1.22

0.87

0.63

Source: Edison Investment Research

Financials

KEFI’s financial results for the half year to 30 June 2015 were consistent both with what investors should expect from a junior mining company and our forecasts. As at 30 June, the company had cash of £1.0m on its balance sheet (cf £0.6m on 31 December 2014) after a cash burn of £3.6m
(cf £3.8m in H114 and £6.3m in FY14). For the purposes of our valuation (and in line with company guidance), we have assumed one further equity raise of US$5m in FY15 via the issue of an additional 619.4m shares (vs 859.4m previously) at a price of 0.53p/share.

On the basis of these assumptions, we estimate that KEFI will have a maximum funding requirement (likely to be satisfied predominantly by debt) of £40.0m (excluding streaming) in FY17 (see Exhibit 8).

Streaming will create an additional contingent liability in KEFI’s accounts, which we estimate in the order of £28.1m at its maximum extent in FY17 (see above and also Exhibit 8). However, streaming is associated with less risk than debt (and is not considered as debt by the lending banks), as it has neither debt-service covenants nor a fixed repayment schedule.

Exhibit 8: Financial summary

£'000s

2013

2014

2015e

2016e

2017e

December

IFRS

IFRS

IFRS

IFRS

IFRS

PROFIT & LOSS

Revenue

 

0

0

0

0

40,859

Cost of Sales

(927)

(2,071)

(1,697)

(1,971)

(31,850)

Gross Profit

(927)

(2,071)

(1,697)

(1,971)

9,010

EBITDA

 

(927)

(2,071)

(1,697)

(1,971)

9,010

Operating Profit (before amort. and except.)

(927)

(2,189)

(1,857)

(5,850)

2,584

Intangible Amortisation

0

0

0

0

0

Exceptionals

(442)

(379)

(200)

0

0

Other

0

0

0

0

0

Operating Profit

(1,369)

(2,568)

(2,057)

(5,850)

2,584

Net Interest

4

(413)

10

(292)

(3,364)

Profit Before Tax (norm)

 

(923)

(2,602)

(1,847)

(6,143)

(780)

Profit Before Tax (FRS 3)

 

(1,365)

(2,981)

(2,047)

(6,143)

(780)

Tax

0

0

0

0

0

Profit After Tax (norm)

(923)

(2,602)

(1,847)

(6,143)

(780)

Profit After Tax (FRS 3)

(1,365)

(2,981)

(2,047)

(6,143)

(780)

Average Number of Shares Outstanding (m)

493.4

952.4

1,799.6

2,363.8

2,363.8

EPS - normalised (p)

 

(0.4)

(0.4)

(0.2)

(0.3)

(0.1)

EPS - normalised and fully diluted (p)

(0.4)

(0.4)

(0.1)

(0.3)

(0.1)

EPS - (IFRS) (p)

 

(0.3)

(0.3)

(0.1)

(0.3)

(0.0)

Dividend per share (p)

0.0

0.0

0.0

0.0

0.0

Gross Margin (%)

-

-

-

-

22.1

EBITDA Margin (%)

-

-

-

-

22.1

Operating Margin (before GW and except.) (%)

-

-

-

-

6.3

BALANCE SHEET

Fixed Assets

 

7,152

9,299

15,791

61,313

79,460

Intangible Assets

6,900

9,139

10,688

9,800

8,912

Tangible Assets

252

160

3,879

50,289

69,324

Investments

0

0

1,224

1,224

1,224

Current Assets

 

4,014

1,061

508

3,679

6,849

Stocks

0

0

0

1,702

3,405

Debtors

655

335

422

1,890

3,358

Cash

3,279

640

0

0

0

Other

80

86

86

86

86

Current Liabilities

 

(3,363)

(3,202)

(2,296)

(2,300)

(2,456)

Creditors

(3,363)

(3,202)

(2,296)

(2,300)

(2,456)

Short term borrowings

0

0

0

0

0

Long Term Liabilities

 

0

0

(2,658)

(45,247)

(68,076)

Long term borrowings

0

0

(2,658)

(15,702)

(40,000)

Other long term liabilities

0

0

0

(29,545)

(28,076)

Net Assets

 

7,803

7,158

11,345

17,445

15,777

CASH FLOW

Operating Cash Flow

 

(1,424)

(2,006)

(2,690)

(5,138)

5,995

Net Interest

4

(413)

10

(292)

(3,364)

Tax

0

0

0

0

0

Capex

(877)

(3,133)

(7,540)

(50,289)

(25,460)

Acquisitions/disposals

(1,083)

(750)

0

0

0

Financing

4,735

3,663

6,922

13,131

0

Dividends

0

0

0

0

0

Net Cash Flow

1,355

(2,639)

(3,298)

(42,588)

(22,829)

Opening net debt/(cash)

 

(1,924)

(3,279)

(640)

2,658

45,247

HP finance leases initiated

0

0

0

0

0

Other

0

0

0

0

0

Closing net debt/(cash)

 

(3,279)

(640)

2,658

45,247

68,076

Source: Company sources, Edison Investment Research

Edison, the investment intelligence firm, is the future of investor interaction with corporates. Our team of over 100 analysts and investment professionals work with leading companies, fund managers and investment banks worldwide to support their capital markets activity. We provide services to more than 400 retained corporate and investor clients from our offices in London, New York, Frankfurt, Sydney and Wellington. Edison is authorised and regulated by the Financial Conduct Authority (www.fsa.gov.uk/register/firmBasicDetails.do?sid=181584). Edison Investment Research (NZ) Limited (Edison NZ) is the New Zealand subsidiary of Edison. Edison NZ is registered on the New Zealand Financial Service Providers Register (FSP number 247505) and is registered to provide wholesale and/or generic financial adviser services only. Edison Investment Research Inc (Edison US) is the US subsidiary of Edison and is regulated by the Securities and Exchange Commission. Edison Investment Research Limited (Edison Aus) [46085869] is the Australian subsidiary of Edison and is not regulated by the Australian Securities and Investment Commission. Edison Germany is a branch entity of Edison Investment Research Limited [4794244]. www.edisongroup.com

DISCLAIMER
Copyright 2015 Edison Investment Research Limited. All rights reserved. This report has been commissioned by KEFI Minerals and prepared and issued by Edison for publication globally. All information used in the publication of this report has been compiled from publicly available sources that are believed to be reliable, however we do not guarantee the accuracy or completeness of this report. Opinions contained in this report represent those of the research department of Edison at the time of publication. The securities described in the Investment Research may not be eligible for sale in all jurisdictions or to certain categories of investors. This research is issued in Australia by Edison Aus and any access to it, is intended only for "wholesale clients" within the meaning of the Australian Corporations Act. The Investment Research is distributed in the United States by Edison US to major US institutional investors only. Edison US is registered as an investment adviser with the Securities and Exchange Commission. Edison US relies upon the "publishers' exclusion" from the definition of investment adviser under Section 202(a)(11) of the Investment Advisers Act of 1940 and corresponding state securities laws. As such, Edison does not offer or provide personalised advice. We publish information about companies in which we believe our readers may be interested and this information reflects our sincere opinions. The information that we provide or that is derived from our website is not intended to be, and should not be construed in any manner whatsoever as, personalised advice. Also, our website and the information provided by us should not be construed by any subscriber or prospective subscriber as Edison’s solicitation to effect, or attempt to effect, any transaction in a security. The research in this document is intended for New Zealand resident professional financial advisers or brokers (for use in their roles as financial advisers or brokers) and habitual investors who are “wholesale clients” for the purpose of the Financial Advisers Act 2008 (FAA) (as described in sections 5(c) (1)(a), (b) and (c) of the FAA). This is not a solicitation or inducement to buy, sell, subscribe, or underwrite any securities mentioned or in the topic of this document. This document is provided for information purposes only and should not be construed as an offer or solicitation for investment in any securities mentioned or in the topic of this document. A marketing communication under FCA Rules, this document has not been prepared in accordance with the legal requirements designed to promote the independence of investment research and is not subject to any prohibition on dealing ahead of the dissemination of investment research.
Edison has a restrictive policy relating to personal dealing. Edison Group does not conduct any investment business and, accordingly, does not itself hold any positions in the securities mentioned in this report. However, the respective directors, officers, employees and contractors of Edison may have a position in any or related securities mentioned in this report. Edison or its affiliates may perform services or solicit business from any of the companies mentioned in this report. The value of securities mentioned in this report can fall as well as rise and are subject to large and sudden swings. In addition it may be difficult or not possible to buy, sell or obtain accurate information about the value of securities mentioned in this report. Past performance is not necessarily a guide to future performance. Forward-looking information or statements in this report contain information that is based on assumptions, forecasts of future results, estimates of amounts not yet determinable, and therefore involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of their subject matter to be materially different from current expectations. For the purpose of the FAA, the content of this report is of a general nature, is intended as a source of general information only and is not intended to constitute a recommendation or opinion in relation to acquiring or disposing (including refraining from acquiring or disposing) of securities. The distribution of this document is not a “personalised service” and, to the extent that it contains any financial advice, is intended only as a “class service” provided by Edison within the meaning of the FAA (ie without taking into account the particular financial situation or goals of any person). As such, it should not be relied upon in making an investment decision. To the maximum extent permitted by law, Edison, its affiliates and contractors, and their respective directors, officers and employees will not be liable for any loss or damage arising as a result of reliance being placed on any of the information contained in this report and do not guarantee the returns on investments in the products discussed in this publication. FTSE International Limited (“FTSE”) © FTSE 2015. “FTSE®” is a trade mark of the London Stock Exchange Group companies and is used by FTSE International Limited under license. All rights in the FTSE indices and/or FTSE ratings vest in FTSE and/or its licensors. Neither FTSE nor its licensors accept any liability for any errors or omissions in the FTSE indices and/or FTSE ratings or underlying data. No further distribution of FTSE Data is permitted without FTSE’s express written consent.

Frankfurt +49 (0)69 78 8076 960

Schumannstrasse 34b

60325 Frankfurt

Germany

London +44 (0)20 3077 5700

280 High Holborn

London, WC1V 7EE

United Kingdom

New York +1 646 653 7026

245 Park Avenue, 39th Floor

10167, New York

US

Sydney +61 (0)2 9258 1161

Level 25, Aurora Place

88 Phillip St, Sydney

NSW 2000, Australia

Wellington +64 (0)48 948 555

Level 15, 171 Featherston St

Wellington 6011

New Zealand

Frankfurt +49 (0)69 78 8076 960

Schumannstrasse 34b

60325 Frankfurt

Germany

London +44 (0)20 3077 5700

280 High Holborn

London, WC1V 7EE

United Kingdom

New York +1 646 653 7026

245 Park Avenue, 39th Floor

10167, New York

US

Sydney +61 (0)2 9258 1161

Level 25, Aurora Place

88 Phillip St, Sydney

NSW 2000, Australia

Wellington +64 (0)48 948 555

Level 15, 171 Featherston St

Wellington 6011

New Zealand

More on KEFI Gold and Copper

View All

Latest from the Metals & Mining sector

View All Metals & Mining content

Metals & Mining

Sayona Mining — Catching up with majors

Metals & Mining

Alphamin Resources — From alpha to omega

Metals & Mining

Pan African Resources — Tennant Creek acquisition

Probiodrug — Update 22 September 2015

Probiodrug

Continue Reading

Subscribe to Edison

Get access to the very latest content matched to your personal investment style.

Sign up for free