H122 operational analysis
Barberton underground (37% of production; 27% of adjusted EBITDA)
Barberton continued to reap the benefits of increased mining flexibility in H122 with the establishment of four platforms from which to cycle high-grade production at the Main Reef Complex (MRC) orebody. Notwithstanding being in line with Barberton’s mine plan, gold production was nevertheless 6% lower than in both H121 and H221 as a result of:
■
Reduced mining rates at the high-grade 42 Level block within New Consort Mine’s Prince Consort (PC) Shaft project area while additional access points to the down-dip extension on 43 Level were being established.
■
Sheba Mine’s Zwartkoppie (ZK) Shaft hoisting being switched to a newly commissioned winder that required the sheath wheels to be realigned and the steel frame headgear to be stabilised. This resulted in the suspension of ore hoisting for a seven-day period while this changeover was effected.
■
Waste development at Fairview Mine to access the high grade 259 platform within the MRC orebody; however, high grade ore on the 259 platform elevation was intersected (as expected) in Q1 CY22.
As a result, although adjusted EBITDA at Barberton decreased relative to H121, the decrease was relative to a record high and it nevertheless more than covered capex of ZAR183.3m. In addition, the improved flexibility resulting from accelerated underground development programmes has now increased the face length available for mining to over 200m (cf 130m at end-FY20) while, at the 257 platform, geological mapping and reserve delineation drilling have identified mineralised widths in excess of 15m (cf the usual 7m ordinarily encountered on the upper platforms).
Exhibit 4: Barberton underground operational statistics and estimates, H118–H222e
|
H118 |
H218 |
H119 |
H219 |
H120 |
H220 |
H121 |
H221 |
H122 |
H122 vs H221 (%) |
H222e |
Tonnes milled underground (t) |
124,969 |
112,862 |
127,858 |
119,777 |
117,545 |
116,035 |
122,199 |
133,473 |
125,257 |
-6.2 |
126,228 |
Head grade underground (g/t) |
8.70 |
12.07 |
9.60 |
9.88 |
*9.70 |
*8.79 |
11.25 |
*10.42 |
*10.46 |
0.4 |
9.62 |
Underground gold contained (oz) |
34,956 |
43,803 |
39,463 |
38,052 |
36,648 |
32,791 |
44,195 |
44,724 |
42,125 |
-5.8 |
39,057 |
Tonnes milled surface (t) |
0 |
0 |
12,471 |
33,158 |
47,231 |
56,593 |
39,267 |
30,078 |
27,740 |
-7.8 |
30,379 |
Head grade surface (g/t) |
0.00 |
0.00 |
2.30 |
1.62 |
*2.16 |
*0.73 |
1.06 |
*0.98 |
*0.98 |
0.1 |
0.98 |
Surface gold contained (oz) |
0 |
0 |
922 |
1,729 |
3,283 |
1,331 |
1,343 |
949 |
876 |
-7.7 |
957 |
Tons milled (t) |
124,969 |
112,862 |
140,329 |
152,935 |
164,776 |
172,628 |
161,466 |
163,551 |
152,997 |
-6.5 |
156,607 |
Head grade (g/t) |
8.70 |
12.07 |
8.95 |
8.09 |
7.54 |
6.15 |
8.77 |
8.69 |
8.74 |
0.6 |
7.95 |
Contained gold (oz) |
34,956 |
43,803 |
40,386 |
39,780 |
39,932 |
34,122 |
45,538 |
45,673 |
43,001 |
-5.9 |
40,014 |
Recovery (%) |
93.0 |
93.5 |
94.0 |
92.5 |
92.0 |
92.0 |
93.0 |
93.0 |
93.0 |
0.0 |
92.5 |
Production underground (oz) |
32,159 |
40,966 |
37,735 |
35,129 |
36,737 |
31,392 |
42,350 |
42,476 |
39,991 |
-5.9 |
37,009 |
Production calcine dumps/surface ops (oz) |
0 |
0 |
815 |
1,677 |
0 |
0 |
0 |
0 |
0 |
|
|
Total production (oz) |
32,159 |
40,966 |
38,550 |
36,806 |
36,737 |
31,392 |
42,350 |
42,476 |
39,991 |
-5.9 |
37,009 |
Recovered grade (g/t) |
8.00 |
11.29 |
8.54 |
7.49 |
6.93 |
5.66 |
8.16 |
8.08 |
8.13 |
0.6 |
7.35 |
|
|
|
|
|
|
|
|
|
|
|
|
Gold sold (oz) |
32,159 |
40,966 |
37,829 |
37,527 |
36,737 |
31,392 |
42,350 |
42,476 |
39,308 |
-7.5 |
37,009 |
Average spot price (US$/oz) |
1,288 |
1,317 |
1,220 |
1,306 |
1,477 |
1,647 |
1,877 |
1,805 |
1,792 |
-0.7 |
1,900 |
|
|
|
|
|
|
|
|
|
|
|
|
Average spot price (ZAR/kg) |
554,361 |
521,029 |
556,770 |
596,180 |
698,031 |
882,504 |
981,381 |
843,828 |
866,671 |
2.7 |
911,016 |
|
|
|
|
|
|
|
|
|
|
|
|
Total cash cost (US$/oz) |
1,145 |
981 |
996 |
1,097 |
1,159 |
1,053 |
997 |
1,150 |
1,227 |
6.7 |
1,283 |
Total cash cost (ZAR/kg) |
492,826 |
390,220 |
454,164 |
500,214 |
547,594 |
572,432 |
521,351 |
542,629 |
593,380 |
9.4 |
615,160 |
Total cash cost (US$/t) |
294.62 |
356.03 |
268.42 |
269.10 |
258.39 |
191.44 |
261.64 |
298.72 |
315.34 |
5.6 |
303.19 |
Total cash cost (ZAR/t) |
3,945.00 |
4,405.46 |
3,860.00 |
3,817.67 |
3,797.00 |
3,237.70 |
4,253.00 |
4,383.29 |
4,742.00 |
8.2 |
4,521.57 |
|
|
|
|
|
|
|
|
|
|
|
|
Implied revenue (US$000) |
41,421 |
53,057 |
46,151 |
49,325 |
54,261 |
53,724 |
79,491 |
76,250 |
70,440 |
-7.6 |
70,317 |
Implied revenue (ZAR000) |
554,499 |
660,698 |
655,098 |
699,398 |
797,598 |
893,997 |
1,292,694 |
1,105,899 |
1,059,597 |
-4.2 |
1,048,671 |
Implied revenue (£000) |
31,422 |
38,722 |
35,652 |
38,120 |
43,061 |
42,614 |
60,824 |
54,762 |
51,680 |
-5.6 |
52,856 |
|
|
|
|
|
|
|
|
|
|
|
|
Implied cash costs (US$000) |
36,819 |
40,182 |
37,667 |
41,155 |
42,576 |
33,047 |
42,246 |
48,857 |
48,246 |
-1.3 |
47,481 |
Implied cash costs (ZAR000) |
493,003 |
497,209 |
534,400 |
583,855 |
625,654 |
558,918 |
686,715 |
716,891 |
725,512 |
1.2 |
708,111 |
Implied cash costs (£000) |
27,900 |
29,269 |
29,102 |
31,803 |
33,796 |
26,203 |
32,349 |
35,265 |
35,413 |
0.4 |
35,682 |
|
|
|
|
|
|
|
|
|
|
|
|
Reported adjusted EBITDA (ZAR000) |
72,300 |
174,700 |
137,200 |
140,700 |
205,100 |
262,200 |
543,900 |
421,700 |
341,000 |
-19.1 |
|
Source: Pan African Resources, Edison Investment Research. Note: *Estimated.
Although the increase in Barberton’s unit working costs of 8.2% (in ZAR/t terms) was above average group, it should be seen within the context of the following company-wide increases in costs:
■
Salaries and wages (representing 26.7% of the total cost of production) increased by 14.2% in US dollar terms and by 5.7% in rand terms. After the end of FY21, Pan African announced a three-year wage agreement with the National Union of Mineworkers (NUM) and a five-year wage agreement with the United Association of South Africa union (UASA). While there were a number of conditions to the agreements, the substantive points were that the NUM deal provided for an average annual wage increase of c 5.6% for three years ending 30 June 2024, while the UASA deal provided for 5.0% increases for the five years to end June 2026, but with the potential to be higher or lower increases depending on the rate of South African consumer price inflation. At the time, the blended average annual increase was expected to be 5.4% compound annually for the initial three-year period of the agreements, compared with which the actual level in the period under review was 5.0% in year-on-year terms (note that the consumer price inflation level in South Africa in December was 5.9%).
■
Mining and processing costs (representing 41.2% of the total cost of production) increased by 12.3% in US dollar terms and 3.9% in rand terms, but with an above average increase being experienced at Barberton owing to increased support installed in working areas with challenging ground conditions.
■
Electricity costs (representing 15.8% of the total cost of production) increased by 10.3% in US dollar terms and 2.4% in rand terms, but which compared to a 15.63% increase in the regulated tariff.
■
Engineering and technical costs (representing 9.2% of the cost of production) increased by 20.5% in US dollar terms and 11.8% in rand terms owing to increased secondary support installed in working areas with challenging ground conditions and an increase in the engineering cost for repairs and maintenance carried out on the load haul drivers at Barberton.
■
Security costs (representing 3.6% of the cost of production) increased by 2.6% in US dollar terms but decreased by 3.3% in rand terms as a result of cost reduction initiatives.
The PC Shaft Level 42 project at Barberton’s New Consort operation contributed significantly to production in the prior year period. Following this performance, a cemented backfill grout plant was commissioned at New Consort to assist in supporting the poor ground conditions associated with the highly altered (but high grade) schistose orebody and also volume extraction. Secondary support on the strike and down-dip extensions of the orebody is being installed, while the final cuts of the 42 Level block are extracted, albeit at a slower rate owing to unfavourable ground conditions. It is envisaged that the down-dip extension of the orebody will then be accessed during the fourth quarter of FY22. Further high-grade mineralisation has also been identified on the PC Shaft’s 20 Level, where exploration and establishment activities are underway.
In the meantime, mining of the high-grade Thomas and Verster orebodies at Sheba has assisted in maintaining the mine’s production profile over the past two reporting periods. Development on the 37 Level haulage in the ZK orebody has intersected high-grade cross-fractures, which are currently being explored and also prepared for mining activities. Elsewhere, Project Dibanisa (which effectively connects the underground workings of the Fairview and Sheba mines), is progressing on schedule. This project is aimed at decreasing the operational cost of the Sheba operation by hoisting the ore from Sheba Mine’s MRC Shaft, utilising Fairview Mine’s infrastructure above 2 decline and is scheduled for completion by the end of FY22, with the first Sheba ore expected to be hoisted at Fairview in FY23. It will also create further capacity at Sheba Mine’s ZK Shaft for the hoisting of Royal Sheba ore from 23 Level, when the 23 Level development intersects the Royal Sheba lowers, which will significantly reduce Royal Sheba’s capital requirements.
In the period under review, Barberton Mines conducted 5,003m of near-mine and exploration drilling (cf 3,502m in H121) in order to delineate and de-risk the near-term mine schedule. Plans for the next six months at Barberton Mines include an increase in near-mine and broader-scale exploration drilling, with exploration targets including the Hope Reef, MRC, Consort Contact Reef and Main Muiden Reef. Desktop studies are also being conducted on various other known but unmined lower-grade resource blocks.
Elikhulu (24% of production; 29% of adjusted EBITDA)
Gold production at Elikhulu increased by 5.3% in H122 cf H221 as a result of a 16.8% increase in the grade in the material mined and despite a 13.2% decline in plant recoveries as a result of higher than expected concentrations of historically processed fine carbon in the lower benches of the Kinross tailings storage facility (TSF), which adversely affected metallurgical recoveries, compounded by the mining of the coarser but high-grade outer wall of the Kinross TSF, which also acted to reduce recoveries. In addition, operations were disrupted by above average rainfall and associated thunder storms in November and December.
As a result, whereas we calculated that Elikhulu accounted for 47% of group-wide H120 adjusted EBITDA, 91% of H220 adjusted EBITDA and 68% of FY20 adjusted EBITDA, since then we estimate that it accounted for 39% of H121 adjusted EBITDA, 27% of H221 adjusted EBITDA, 33% of FY21 adjusted EBITDA and 29% of H122 adjusted EBITDA. Nevertheless, while adjusted EBITDA at Elikhulu was comparable in magnitude to that of both Barberton and Evander (see Exhibit 2), its capex was still an order of magnitude lower (eg ZAR28.9m cf c ZAR160m), such that it almost certainly remained the largest contributor to the group’s operational cash flow.
Exhibit 5: Elikhulu operational statistics and estimates, H119–H222e
|
H119 |
H219 |
H120 |
H220 |
H121 |
H221 |
H122 |
H122 cf H221 (%) |
H222e |
Tonnes processed tailings (t) |
3,534,278 |
7,313,931 |
6,211,028 |
6,882,546 |
6,278,191 |
6,776,576 |
6,442,397 |
-4.9 |
6,702,545 |
Head grade tailings (g/t) |
0.30 |
0.26 |
*0.28 |
0.32 |
0.31 |
0.29 |
0.34 |
16.8 |
0.25 |
Tailings gold contained (oz) |
34,089 |
60,199 |
56,348 |
70,494 |
62,472 |
63,038 |
70,000 |
11.0 |
53,590 |
Recovery (%) |
44.0 |
51.3 |
52.0 |
43.0 |
43.0 |
42.6 |
37.0 |
-13.2 |
47.8 |
Production tailings (oz) |
15,292 |
30,909 |
29,301 |
30,315 |
26,863 |
24,596 |
25,900 |
5.3 |
25,600 |
|
|
|
|
|
|
|
|
|
|
Total production (oz) |
15,292 |
30,909 |
29,301 |
30,315 |
26,863 |
24,596 |
25,900 |
5.3 |
25,600 |
Recovered grade (g/t) |
0.13 |
0.13 |
0.15 |
0.14 |
0.13 |
0.11 |
0.13 |
10.8 |
0.12 |
|
|
|
|
|
|
|
|
|
|
Gold sold (oz) |
15,292 |
30,173 |
29,301 |
30,315 |
26,863 |
24,596 |
25,900 |
5.3 |
25,600 |
Average spot price (US$/oz) |
1,216 |
1,306 |
1,451 |
1,647 |
1,852 |
1,805 |
1,813 |
0.4 |
1,900 |
|
|
|
|
|
|
|
|
|
|
Average spot price (ZAR/kg) |
563,250 |
596,180 |
685,680 |
882,504 |
968,130 |
843,828 |
876,640 |
3.9 |
911,016 |
|
|
|
|
|
|
|
|
|
|
Total cash cost (US$/oz) |
517 |
575 |
621 |
495 |
656 |
849 |
806 |
-5.0 |
772 |
Total cash cost (ZAR/kg) |
239,639 |
262,650 |
293,608 |
265,166 |
342,917 |
396,698 |
389,660 |
-1.8 |
370,380 |
Total cash cost (US$/t) |
2.24 |
2.43 |
2.93 |
2.15 |
2.81 |
3.05 |
3.24 |
6.3 |
2.95 |
Total cash cost (ZAR/t) |
32.00 |
33.70 |
43.00 |
36.33 |
45.63 |
44.78 |
48.72 |
8.8 |
44.00 |
|
|
|
|
|
|
|
|
|
|
Implied revenue (US$000) |
18,595 |
39,009 |
42,516 |
50,783 |
49,750 |
43,442 |
46,957 |
8.1 |
48,640 |
Implied revenue (ZAR000) |
267,899 |
554,999 |
624,898 |
837,196 |
808,898 |
626,289 |
706,198 |
12.8 |
725,390 |
Implied revenue (£000) |
14,365 |
30,145 |
33,740 |
40,283 |
38,067 |
31,097 |
34,451 |
10.8 |
36,562 |
|
|
|
|
|
|
|
|
|
|
Implied cash costs (US$000) |
7,912 |
17,742 |
18,209 |
14,818 |
17,626 |
20,657 |
20,874 |
1.1 |
19,775 |
Implied cash costs (ZAR000) |
114,000 |
246,492 |
267,600 |
250,023 |
286,500 |
303,480 |
313,900 |
3.4 |
294,912 |
Implied cash costs (£000) |
6,208 |
13,421 |
14,455 |
11,784 |
13,496 |
14,986 |
15,322 |
2.2 |
14,861 |
|
|
|
|
|
|
|
|
|
|
Adjusted EBITDA (ZAR000) |
145,100 |
296,300 |
333,100 |
564,000 |
484,800 |
301,200 |
367,000 |
21.8 |
|
Source: Pan African Resources, Edison Investment Research. Note: *Estimate.
Elikhulu’s AISC increased by 27.1% to US$937/oz relative to the prior year period, mainly owing to an increase in salary costs as a result of a change in the incentive structure, an increase in headcount and a decrease in recoveries and production.
Capex at Elikhulu will continue to increase in FY22 as it transitions from Phase 1 of its operations (the re-mining of Kinross tailings) to Phase 2 (the re-mining of Leslie and Bracken tailings), necessitating the installation of approximately 6km of piping and a pump station between the plant and the areas to be mined. Thereafter, it is expected to produce approximately 60,000oz gold pa until FY26. For the final seven years of operation, as re-mining transitions to the Winkelhaak tailings storage facility (TSF), Elikhulu is expected to produce c 50,000oz gold pa (excluding c 102,000oz inferred mineral resources delineated in the soil material beneath the existing TSFs).
In the current year, we expect Elikhulu to produce 51,500oz gold (see Exhibit 1), with improved throughput and higher recoveries from the planned re-mining of areas on the upper benches of the number three Kinross TSF dam (in line with its mine plan from the start of production).
Evander underground (25% of production; 32% of adjusted EBITDA)
Relative to prior periods, underground operations at Evander in H221 recorded a vastly improved performance, with both tonnes processed and grades increasing materially at the same time that unit costs (measured in ZAR/t) decreased materially, to result in a near seven-fold increase in adjusted EBITDA (cf H121) to a level that is a record for underground operations at Evander since they came under Pan African ownership and management in H213.
Exhibit 6: Evander operational statistics and estimates, H119–H222e
|
H119 |
H219 |
H120 |
H220 |
H121 |
H221 |
H122 |
Change (%)* |
H222e |
Tonnes milled (t) |
37,347 |
26,624 |
30,044 |
21,392 |
50,634 |
69,812 |
69,790 |
0.0 |
70,000 |
Head grade (g/t) |
7.82 |
10.01 |
12.59 |
5.16 |
8.51 |
10.56 |
12.55 |
18.8 |
8.27 |
Contained gold (oz) |
9,384 |
8,572 |
12,161 |
3,549 |
13,854 |
23,709 |
28,157 |
18.8 |
18,602 |
Recovery (%) |
94 |
94 |
95 |
94 |
91 |
99 |
97 |
-1.8 |
98 |
Underground production (oz) |
8,821 |
8,058 |
11,553 |
9,117 |
12,607 |
23,409 |
27,312 |
16.7 |
18,230 |
Production from surface sources (oz) |
0 |
0 |
0 |
0 |
|
|
|
|
|
Total production (oz) |
8,821 |
8,058 |
11,553 |
9,117 |
12,607 |
23,409 |
27,312 |
16.7 |
18,230 |
Recovered grade (g/t) |
7.35 |
9.41 |
11.96 |
13.26 |
7.74 |
10.43 |
12.17 |
16.7 |
8.10 |
|
|
|
|
|
|
|
|
|
|
Gold sold (oz) |
8,821 |
8,058 |
9,214 |
5,863 |
12,607 |
23,409 |
27,312 |
16.7 |
18,230 |
Average spot price (US$/oz) |
1,214 |
1,306 |
1,451 |
1,647 |
1,852 |
1,805 |
1,813 |
0.4 |
1,900 |
|
|
|
|
|
|
|
|
|
|
Average spot price (ZAR/kg) |
565,367 |
596,180 |
685,658 |
882,504 |
968,072 |
843,828 |
876,639 |
3.9 |
911,016 |
|
|
|
|
|
|
|
|
|
|
Total cash cost (US$/oz) |
1,711 |
1,814 |
1,420 |
1,241 |
1,604 |
1,030 |
915 |
-11.2 |
902 |
Total cash cost (ZAR/kg) |
780,357 |
828,170 |
671,299 |
665,209 |
838,665 |
481,582 |
442,226 |
-8.2 |
432,397 |
Total cash cost (US$/t) |
404.07 |
549.62 |
546.00 |
169.14 |
399.31 |
342.36 |
357.95 |
4.6 |
234.85 |
Total cash cost (ZAR/t) |
5,733 |
7,796 |
6,404 |
5,671 |
6,496 |
5,023 |
5,383 |
7.2 |
3,502 |
|
|
|
|
|
|
|
|
|
|
Implied revenue (US$000) |
10,709 |
10,525 |
13,370 |
9,879 |
23,348 |
41,877 |
49,517 |
18.2 |
34,636 |
Implied revenue (ZAR000) |
155,115 |
146,084 |
196,499 |
167,699 |
379,599 |
624,798 |
744,697 |
19.2 |
516,546 |
Implied revenue (£000) |
8,272 |
8,134 |
10,610 |
7,836 |
17,865 |
30,543 |
36,329 |
18.9 |
26,035 |
|
|
|
|
|
|
|
|
|
|
Implied cash costs (US$000) |
15,091 |
14,633 |
16,404 |
3,618 |
20,218 |
23,901 |
24,981 |
4.5 |
16,439 |
Implied cash costs (ZAR000) |
214,100 |
207,564 |
192,402 |
121,306 |
328,918 |
350,638 |
375,680 |
7.1 |
245,169 |
Implied cash costs (£000) |
11,659 |
11,301 |
10,393 |
5,509 |
15,495 |
17,312 |
18,337 |
5.9 |
12,354 |
|
|
|
|
|
|
|
|
|
|
Adjusted EBITDA (ZAR000) |
(58,985) |
26,085 |
64,900 |
(345,600) |
49,000 |
331,000 |
408,500 |
23.4 |
|
Source: Pan African Resources, Edison Investment Research. Note: *H122 cf H221.
The increase in unit working costs at Evander could be attributed to:
■
Production incentives paid in relation to increased production.
■
Increased support costs relating to the 8 Shaft pillar.
■
A 5.6% average increase in reagent costs.
■
The capitalisation of electricity costs associated with the 24 Level development leading to a decrease of 9.3% in Evander Mines’ underground electricity costs.
Gold production from the 8 Shaft pillar is expected to reduce in H222 as mining progresses to areas with lower estimated grades. As per its mine plan, the 8 Shaft pillar now has a remaining life of approximately one and a half years, during which time it is expected to produce c 60,000oz gold at a rate of c 40,000oz pa. Mining at 24 Level will then extend 8 Shaft’s production profile, post cessation of the 8 Shaft pillar mining, for an additional two and a half years and maintain annual production at c 34,000oz pa. Mining from this level is anticipated to commence in FY23, as the current pillar mining reaches completion, after which the board has also now approved the development capital for Evander’s 25 and 26 Level project, which is expected to increase the 8 Shaft’s life of mine to 13 years at an expected annual production rate of approximately 65,000oz.